Preferred Language
Articles
/
joe-2552
Development a Proposed System of Organization Structure to Management Multi Construction Projects
...Show More Authors

The purpose of this study is aimed to lay down an arranged platform suited to Iraqi constructional associations which in charge to carry out multi constructional projects, as it fulfilled management requirements and supervising, so that low - cost projects will be controlled in due term and quality. Based on primary info and observed data collected, the study thesis has been formulated in this way: Iraqi constructional sector bodies which are in charge to implement simultaneously multi constructional projects in need to reformulate its organized structure so that it will be more fitted to management and control of these projects. This thesis includes a
theoretical part contained presenting the most important resources locally and internationally where it has direct relation with this study subject. Also it touches on the arrangement term and the kinds of organized structure of the multi constructional projects and control it. And its field part included in its first section studying the organized structure and functional arrangement practised in one of the Iraqi constructional projects. in charge of implemented simultaneously multi construction and exposing the defection of this arrangement. The second section of this study included reviewing the organized structure used by some of constructed corporations and foreign companies of implementing multi constructional projects .Thus, the deficiency points of the organized structure and the arrangement followed in Iraqi conduction sectors recognized and what it causes of control defections in the limitation of these
projects. The deficiency points have been solved by developing a proposed system of the organized structure to administering and controlling of the multi constructional projects. The implementation of these projects have been controlled from its draw phase and passing the design phase and reference and implementation phase till the first deliver.

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Mon Feb 08 2021
Journal Name
Public Works Management & Policy
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security is

... Show More
View Publication
Scopus (17)
Crossref (21)
Scopus Clarivate Crossref
Publication Date
Tue Nov 09 2021
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
The role of integration between the earned value management model and the value flow map in rationalizing the costs of construction projects: applied research in Al-Rasheed General Company for Construction Contracting
...Show More Authors

The research problem is that most of the construction projects exceed the planned value, due to the failure to implement the plans on time. The current study aims to monitor the implementation of the project and for each of the executed tasks of the table of quantities in order to detect deviations at the time they occur, evaluate the time and cost performance, and then identify the areas of waste and analyze the implementation of each task in order to diagnose the underlying problems and find possible and applicable solutions in the environment Iraqi. The research was applied in one of the companies specialized in the field of construction projects, and one of the most important conclusions reached is the possibility of applying

... Show More
View Publication Preview PDF
Publication Date
Sun Apr 30 2017
Journal Name
Journal Of Engineering
Implementation of a Proposed Load-Shedding System Using Altera DE2 FPGA
...Show More Authors

A load-shedding controller suitable for small to medium size loads is designed and implemented based on preprogrammed priorities and power consumption for individual loads. The main controller decides if a particular load can be switched ON or not according to the amount of available power generation, load consumption and loads priorities. When themaximum allowed power consumption is reached and the user want to deliver power to additional load, the controller will decide if this particular load should be denied receiving power if its priority is low. Otherwise, it can be granted to receive power if its priority is high and in this case lower priority loads are automatically switched OFF in order not to overload the power generation. The

... Show More
View Publication Preview PDF
Publication Date
Mon Jun 01 2009
Journal Name
Journal Of Economics And Administrative Sciences
Using the Box Jenkins models to predict Iraq's cement production and to demonstrate its adequacy under future construction projects
...Show More Authors

تعد صناعة السمنت في العراق من اقدم الصناعات الحديثة واكثرها تطورا وتقدما ومن اقواها تاثيرا في الاقتصاد القومي. واذ توفر في صناعة السمنت العراقي كافة المستلزمات الناجحة من حيث توفر المواد الاولية والخبرات الفنية والتقنية واسواق ثابتة وراسخة محليا وعالميا فقد كان من المفروض ان يتم التوسع في هذه الصناعة، وان التخطيط لهذه الصناعة امرا ضروريا خاصة وان مادة السمنت هي احدى اهم المواد الرئيسة التي يؤثر توفره

... Show More
View Publication Preview PDF
Crossref
Publication Date
Wed Jul 01 2020
Journal Name
Journal Of Engineering
Examining sensitivity of financial performance at construction projects prequalification stage
...Show More Authors

Construction projects are complicated in nature and require many considerations in contractor selection. One of the complicated interactions is that between performance with the project size, and contractor financial status, and size of projects contracted. At the prequalification stage, the financial ‎requirements restrict the ‎contractors to meet minimum limits in financial criteria such as net worth, working capital and ‎annual turnover, etc. In construction projects, however, there are cases when contractors meet these requirements but show low performance in practice. The model used in the study predicts the performance by training of a neural network. The data used in the study are 72 of the most recent roadw

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Oct 02 2023
Journal Name
Journal Of Engineering
Main Delay Factors of Implementation EPC Construction Projects in Iraq
...Show More Authors

This essay aims to highlight the most important issues and difficulties facing implementing large projects that follow the turn-key method, considered one of the types of contractual methods in Iraq, especially for large and complex projects requiring speedy completion. The projects implemented in this way face delays and delays in completion, which led to the lack of benefit from the projects for which they were implemented, especially those affecting the lives of citizens within the health sector. The case study dealt with the construction of hospitals with multi-bed capacities within multiple governorates in Iraq, With large financial allocations within the federal budget of the Government of Iraq over several years.

... Show More
View Publication Preview PDF
Crossref (4)
Crossref
Publication Date
Tue Apr 01 2025
Journal Name
Journal Of Economics And Administrative Sciences
Evaluation of Knowledge Management System Requirements According to ISO 30401
...Show More Authors

This Paper assesses the knowledge management system (KMS) requirements at Al-Ameed University concerning ISO 30401:2022. Specifically, the research aims to ascertain the degree to which international standards have been complied with and gaps that have been identified. A case study was conducted using field observations, interviews, and checklists to assess the institution's compliance with the KMS framework. The level of implementation and documentation of knowledge management processes was assessed using a seven-point scale. The findings reveal that Al-Ameed University has severe gaps in knowledge creation, sharing, and support for knowledge management in terms of strategic leadership. While certain elements like availability of r

... Show More
View Publication
Crossref
Publication Date
Sun Apr 30 2017
Journal Name
Journal Of Engineering
Sustainable Roadway Planning: A Model for a Proposed Rating System in Iraq
...Show More Authors

     The goal of the research is to develop a sustainable rating system for roadway projects in Iraq for all of the life cycle stages of the projects which are (planning, design, construction and operation and maintenance). This paper investigates the criteria and its weightings of the suggested roadway rating system depending on sustainable planning activities. The methodology started in suggesting a group of sustainable criteria for planning stage and then suggesting weights from (1-5) points for each one of it. After that data were collected by using a closed questionnaire directed to the roadway experts group in order to verify the criteria weightings based on the relative importance of the roadway related impacts

... Show More
View Publication Preview PDF
Publication Date
Sun Feb 01 2015
Journal Name
Journal Of Engineering
Design a Multi-Choice Fuzzy Control System of the Greenhouse
...Show More Authors

Applications of nonlinear, time variant, and variable parameters represent a big challenge in a conventional control systems, the control strategy of the fuzzy systems may be represents a simple, a robust and an intelligent solution for such applications.

This paper presents a design of fuzzy control system that consists of three sub controllers; a fuzzy temperature controller (FC_T), a fuzzy humidity controller (FC_H) and a ventilation control system; to control the complicate environment of the greenhouse (GH) using a proposed multi-choice control system approach. However, to reduce the cost of the crop production in the GH, the first choice is using the ventilation system to control the temperature and humidit

... Show More
View Publication Preview PDF
Publication Date
Mon Jun 06 2022
Journal Name
Engineering, Technology & Applied Science Research
Supply Chain Management of Infrastructure Projects in Iraq
...Show More Authors

Infrastructure projects take a long time, are complex, multidisciplinary, use different materials and products, and have high risk. These characteristics affect the process of supplying materials. The current paper studies the ability to improve the supply chain process and decrease its cost by identifying the factors that affect it. These factors are used as variables in the mathematical model, which is working under uncertain conditions when the consumption rate of materials is not constant. The information used in this model is obtained from Building Information Modeling (BIM) and Geographical Information System (GIS) techniques and the genetic algorithm is utilized to determine the optimal supplier and the quantities of supplies

... Show More
View Publication
Scopus (6)
Crossref (6)
Scopus Crossref