Preferred Language
Articles
/
jeasiq-988
Scheduling Critical Activities of Stochastic Projects Management
...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Tue Oct 01 2019
Journal Name
Journal Of Economics And Administrative Sciences
Scheduling projects using dynamic programming style and smart algorithm
...Show More Authors

The aim of this research is to compare traditional and modern methods to obtain the optimal solution using dynamic programming and intelligent algorithms to solve the problems of project management.

It shows the possible ways in which these problems can be addressed, drawing on a schedule of interrelated and sequential activities And clarifies the relationships between the activities to determine the beginning and end of each activity and determine the duration and cost of the total project and estimate the times used by each activity and determine the objectives sought by the project through planning, implementation and monitoring to maintain the budget assessed 

... Show More
View Publication Preview PDF
Crossref
Publication Date
Thu Apr 11 2019
Journal Name
Political Sciences Journal
Scientific Activities College of branches
...Show More Authors

Scientific Activities College of branches

View Publication Preview PDF
Crossref
Publication Date
Thu Apr 25 2019
Journal Name
Iraqi Journal Of Market Research And Consumer Protection
PATTERN OF INVESTMENT PROJECTS IN THE INVESTMENT ENVIRONMENT: PATTERN OF INVESTMENT PROJECTS IN THE INVESTMENT ENVIRONMENT
...Show More Authors

That the building of the national economy depends on the extent of the possibility of transition from the rent economy seeking to increase GDP (GDP1), and the tendency to manage projects with external sources of funding, or allow projects with foreign capital is a necessity. The strategic challenges faced by the economy in countries that have experience in investment projects have faced several factors internal and external for a period of time and not a few and the pressures and difficulties and failures have affected in one way or another on the development work in that country. On this basis, the stakeholders have a role to pay attention to the issue of the feasibility of the pattern of foreign investment in the investment environment

... Show More
View Publication Preview PDF
Publication Date
Sun Dec 01 2013
Journal Name
Political Sciences Journal
Scientific Activities The branch of political thought
...Show More Authors

النشاطات العلمية لفرع الفكر السياسي

View Publication Preview PDF
Crossref
Publication Date
Sat Sep 01 2018
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Evaluation of the performance of scheduling The implementation of school buildings projects: (Project of the Ministry of Education No. 1)
...Show More Authors

It highlights the importance of construction projects because of its significant role in the development of society, including the buildings FEDE projects to their importance to raise the level of education through the conclusion of the special to implementation and the establishment of schools of contracts at the country level, which requires the completion of the project at less time and within the cost specified and the best quality and may highlight the importance of time on all the elements of what has an important role in setting up the project for various reasons may be the need for the use of schools as soon as possible, but the reality showed exceeded the completion of those schools could be up to 6 years and there are some cont

... Show More
View Publication Preview PDF
Crossref
Publication Date
Sat Dec 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Measuring the Critical Success Factors for Total Quality Management Applications (Compared research of many colleges)
...Show More Authors

ABSTRACT

This research aim to measure the critical success factors for total quality management applications, in order to know the key and important role played by these factors at applying the total quality management through a comparative study conducted in a number of a private colleges.

The research problem posed a set of questions, the most important ones are: Are the colleges (sample of research) aware of the critical success factors at applying the total quality management? What is the availability of the critical success factors at the work of the colleges (sample of research)? 

What are the critical success factors in the work of the researc

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Mon Oct 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Nurse Scheduling Problem Using Hybrid Simulated Annealing Algorithm
...Show More Authors

Nurse scheduling problem is one of combinatorial optimization problems and it is one of NP-Hard problems which is difficult to be solved as optimal solution. In this paper, we had created an proposed algorithm which it is hybrid simulated annealing algorithm to solve nurse scheduling problem, developed the simulated annealing algorithm and Genetic algorithm. We can note that the proposed algorithm (Hybrid simulated Annealing Algorithm(GS-h)) is the best method among other methods which it is used in this paper because it satisfied minimum average of the total cost and maximum number of Solved , Best and Optimal problems. So we can note that the ratios of the optimal solution are 77% for the proposed algorithm(GS-h), 28.75% for Si

... Show More
View Publication Preview PDF
Crossref
Publication Date
Sun Jan 08 2023
Journal Name
Journal Of Planner And Development
Statistical Evaluation of the Planning Process and Scheduling Management for Irrigation and Drainage Projects in the Republic of Iraq
...Show More Authors

The Research aims to investigate into reality in terms of planning and scheduling management process for sake the implementation and maintenance of irrigation and drainage projects in the Republic of Iraq, with an indication of the most important obstacles that impede the planning and scheduling management process for these projects and ways of addressing them and minimizing their effects.                                                  For the purpose of achieving the goal of the research, a sci

... Show More
View Publication Preview PDF
Publication Date
Fri Apr 01 2022
Journal Name
Baghdad Science Journal
An Evolutionary Algorithm for Solving Academic Courses Timetable Scheduling Problem
...Show More Authors

Scheduling Timetables for courses in the big departments in the universities is a very hard problem and is often be solved by many previous works although results are partially optimal. This work implements the principle of an evolutionary algorithm by using genetic theories to solve the timetabling problem to get a random and full optimal timetable with the ability to generate a multi-solution timetable for each stage in the collage. The major idea is to generate course timetables automatically while discovering the area of constraints to get an optimal and flexible schedule with no redundancy through the change of a viable course timetable. The main contribution in this work is indicated by increasing the flexibility of generating opti

... Show More
View Publication Preview PDF
Scopus (8)
Crossref (3)
Scopus Clarivate Crossref
Publication Date
Tue Mar 01 2016
Journal Name
Journal Of Engineering
Critical Success Factors in Construction Projects (Governmental Projects as a Case Study)
...Show More Authors

The importance of the construction sector and its Great role in the provision of services and infrastructure, reduce poverty, improve living conditions and improve the economic situation in the country, impose attention to the way in which the projects implemented for its improvement and to get successful projects. The objective of this research was to determine the criteria for success as well as critical success and failure factors that have a significant impact on project success. A selected 75 engineer (department managers, project managers and engineers) are asked to fill  the questionnaire form, Sixty-seven valid questionnaire forms were analyzed statistically to get search results, which were as follows : Twe

... Show More
View Publication Preview PDF