...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Tue Oct 01 2019
Journal Name
Journal Of Economics And Administrative Sciences
apply Six Sigma in improving the quality of projects added expert system )Applied research(
...Show More Authors

Construction projects need methods and techniques to ensure the level of quality and commensurate with the level required and documented in the project contract. The quality of the project is affected by the quality of the inputs and accompanying procedures in the construction of the project.

Al-Rumaitha residential project found that the quality of the concrete for the ceilings in the research sample (the roof of the third floor of buildings A25 and A26) and (roof of the second floor of buildings A27, A28, A29, A30, A31, A32 and A33) and roof of buildings A15 and A16 A19)) is not the required quality level.

The idea of the research came after the need to improve the performance o

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Fri Jun 01 2018
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Project Planning & Scheduling: بحث تطبيقي لمشاريع / مديرية الابنية المدرسية /دائرة المشاريع /مشروعالوزارةرقم (1)
...Show More Authors

Construction project life-cycle processes must be managed in a more effective and predictable way to meet project stakeholder needs , However, there is increasing concern about whether know-how effectively improves  understanding of underlying theories of project management processes for construction organizations and their project managers  Project planning and scheduling are considered as key and challenging tools in controlling and monitoring project performance , but many worldwide construction projects appear to give insufficient attention to effective management and definition of  project  planning, including pre planning stages . Indeed, some planning issues indeed, some planning issues have been completely ove

... Show More
View Publication Preview PDF
Crossref
Publication Date
Thu Dec 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
The role of my style (CPM / PERT) in enhancing the performance of construction projectsAn Empirical Study in the Department of projects in the office of the province of Baghdad
...Show More Authors

Abstract

This study was to demonstrate the role-use planning scientific methods is disabled and little used in the planning and follow-up construction of vital projects in the province of Baghdad, including network planning methods, in order to find the optimal time to finish the project in light of the resources available and the budget set for it, in the current research has been used the most prominent network planning methods and two stylistic (CPM / PERT), was the application of the critical path method on standard-design school project (traditional) to draw Action Network according to confirmed times for the activities of the project and account his Crashing time , It was Pert technique applied to the project hemato

... Show More
View Publication Preview PDF
Crossref
Publication Date
Fri Dec 01 2017
Journal Name
Journal Of Economics And Administrative Sciences
“The impact of the critical factors for the transfer of knowledge on opportunities and strategic success”
...Show More Authors

The current research discusses “The impact of the critical factors for the transfer of knowledge on opportunities and strategic success ", the attention have been increased on knowledge transfer and strategic success subjects because on being one of the important and contemporary issues, which have a significant impact on the existence of organizations and its future. The research aims to identify the critical factors for knowledge transfer in private high education environment which enables (the college community surveyed) to achieve strategic success, also the research sought to answer questions related to research problem by testing a number of major and minor hypothes in impact, in order to test the hypotheses I used a fiel

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Tue Nov 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Hiring managers tacit knowledge in the electronic Human Resource Management
...Show More Authors

Abstract
            This research aims to determine the nature of tacit knowledge relationship and its impact on building the electronic human resources management, as it constitutes the most prominent tacit knowledge resources owned by the Organization for being a stand out in the skill, knowledge and intellectual capacity of human resources, as the electronic human resources management is a contemporary trend that adopted by the organization in the performance of all tasks and duties related workers have remained in the contemporary environment in which it operates.

and have indicated the research problem to the low level of awareness of the ad

... Show More
View Publication Preview PDF
Crossref
Publication Date
Wed Dec 01 2021
Journal Name
Civil And Environmental Engineering
Investigating the Critical Success Factors for Water Supply Projects: Case of Iraq
...Show More Authors
Abstract<p>Water supply projects (WSP) requires high plan information, specialized capabilities, capable human resources, and high administrative capacity. However, in the developing countries, particularly in Iraq, these projects experience a lack of a large number of these necessities, which shows the need to identify the critical success factors (CSFs). Accordingly, the objectives of this research are to investigate the CSFs for WSP and their significance among the construction (public and private) and education sectors. To achieve this, first we have carried out a comprehensive literature review of the CSFs for WSP. Second, we administrated a questionnaire survey to 260 construction experts </p> ... Show More
View Publication
Scopus (5)
Crossref (4)
Scopus Clarivate Crossref
Publication Date
Sun Jan 14 2018
Journal Name
Journal Of Engineering
Efficient Cost Management in the Housing Projects
...Show More Authors

The cost management of cost indicators in housing projects, on the level of planning and design, is the most important quality indicators, for adoption of strategies of planning and design efficient in managing these indicators. So this research points out the need to highlight the most effective and influential cost indicators in housing projects, and to determine strategies in the management of these indicators in order to raise the efficiency of housing projects quality, to seemly the income level target group, taking into consideration the quality of housing standards, to achieve the basic requirements of housing. This paper highlights the importance of the cost  management, the types of housing cost, the method

... Show More
View Publication Preview PDF
Publication Date
Mon Jun 06 2022
Journal Name
Engineering, Technology &amp; Applied Science Research
Supply Chain Management of Infrastructure Projects in Iraq
...Show More Authors

Infrastructure projects take a long time, are complex, multidisciplinary, use different materials and products, and have high risk. These characteristics affect the process of supplying materials. The current paper studies the ability to improve the supply chain process and decrease its cost by identifying the factors that affect it. These factors are used as variables in the mathematical model, which is working under uncertain conditions when the consumption rate of materials is not constant. The information used in this model is obtained from Building Information Modeling (BIM) and Geographical Information System (GIS) techniques and the genetic algorithm is utilized to determine the optimal supplier and the quantities of supplies

... Show More
View Publication
Scopus (5)
Crossref (4)
Scopus Crossref
Publication Date
Thu Oct 01 2015
Journal Name
Journal Of Economics And Administrative Sciences
Project Scheduling By using Goals Programming – An Applied Research In Modern Village Project (Residential Building Aspectin In Wasit Governorate)
...Show More Authors

One of the most important challenges facing project management at present time is to ensure project accomplishment in spite of the specific restrictions like the specific time the financial resources specialized to do the project ; which require an accurate consideration for time and cost . the modern village project (residential building aspect) is one of the great project that ministry of agriculture is trying to do Wasit  governorate it is chosen as the work in this project is dilatory for that is being studied in term of some modern mathematical and scientific methods like critical path method (CPM)which is one of the project management and scheduling methods to know the time needed to accomplish residential building pro

... Show More
View Publication Preview PDF
Crossref
Publication Date
Tue Dec 22 2020
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Cost Management of construction industries according to the fast-track method
...Show More Authors

Construction projects have become a changing dramatically in recent decades and that the goal of the beneficiaries of the implementation of structural project is to complete the work with less time and within the cost of the specific and the best possible quality may sometimes happen that highlights the importance of time on the rest of the items at the implementation of projects for various reasons, including the need to use the project as soon as possible possible change rapidly to customer's requests, but the high cost of the project represents the biggest obstacle for entrepreneurs with its effects on the quality and the time workers, and is a measure of those elements in monetary terms is the key to integration between them, so the

... Show More
View Publication Preview PDF