Scheduling Critical Activities of Stochastic Projects Management

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Tue Jun 30 2020
Journal Name
Journal Of Economics And Administrative Sciences
Using the Critical Path Method (CPM) for scheduling the project (paving the Amil Sayid Al-Ayyam Street with a length of 1.25 km) In terms of Decresing the time

The implementation of the concept of project scheduling in the organizations generally requires a set of procedures and requirements, So, most important of all is the understanding and knowledge of the tools and techniques which are called the methods of scheduling projects. Consequently, the projects of the municipality administration in the holy governorate of Karbala suffer from the problem of delaying their projects and chaos in the ways of implementation. To provide assistance to this directorate and to demonstrate how to schedule projects using one of the advanced scientific methods that proved their ability to schedule any project and its potential to accelerate the time of completion, as well as ease of use and effectiven

... Show More
Crossref
View Publication Preview PDF
Publication Date
Sat Apr 01 2017
Journal Name
Journal Of Economics And Administrative Sciences
Risk Analysis of Projects Accordance with the Professional Project Management System: A case- Study Mansur Construction Contracting Company here

The research aims to identify the risks faced by projects and work on the administration, such as those risks by using professional Project Management System (Project Management Professional) by identifying those risks and their impact on the objectives of the project, if they occur and to provide appropriate responses to Ha.autam search application on the draft Law Faculty port by the General Mansour Construction Contracting company has been using a method personal interview with the heads of departments and project managers in the Al-Mansour and tools descriptive and quantitative analysis as was used (likelihood and impact of risk analysis, Ai_kaoa scheme Sbb- effect, analysis of probability and impact, risk matrix (probability

... Show More
Crossref
View Publication Preview PDF
Publication Date
Wed Oct 17 2018
Journal Name
Journal Of Economics And Administrative Sciences
Impact of evaluation of investment projects in achieving competitive strategy

The aim of the research is to determine the impact of evaluation of investment projects after the preparation of investment budgets taking into consideration within the investment budgets the concept of competitive strategy, as the harmony between the preparation of investment budgets and competitive strategy will contribute to the success of economic unity and achieve profits well and achieve a competitive advantage. Strategies for economic units because the most important factor to them is the costs produced and the progress of the research problem is focused on "Is it possible to include a strategy of competition, especially within the investment budget when prepared The study concluded that the investment plan prepared by the

... Show More
Crossref
View Publication Preview PDF
Publication Date
Tue Jun 30 2015
Journal Name
Iraqi Journal Of Market Research And Consumer Protection
Possibilty Of Implementing Hazard Analysis Critical Control Points (HACCP) In One Of Local Dairy Plants.: Possibilty Of Implementing Hazard Analysis Critical Control Points (HACCP) In One Of Local Dairy Plants.

To limit or reduce common microbial contamination occurrence in dairy products in general and in soft cheese in particular, produced in locally plants, this study was performed to demonstrate the possibility of implementing HACCP in one of dairy plants in Baghdad city

            HACCP plan was proposed in soft cheese production line. A pre-evaluation was performed in soft cheese line production, HACCP Pre-requisites programs was evaluated from its presence and effectiveness. The evaluation was demonstrated risk in each of: Good Manufacturing Practice (GMP) program, evaluated as microbial and physical risk and considered as critical r

... Show More
View Publication Preview PDF
Publication Date
Sat Oct 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Improving Nursing process Performance based on service scheduling dimensions. ( Field research)

Abstract :

This present paper sheds the light on dimensions of scheduling the service that includes( the easiness of performing the service, willingness , health factors, psychological sides, family matters ,diminishing the time of waiting that improve  performance of nursing process including ( the willingness of performance, the ability to perform  the performance , opportunity of performance) . There is genuine problem in the Iraqi hospitals  lying into the weakness of nursing staffs , no central decision to define and organize schedules. Thus the researcher has chosen  this problem as to be his  title . The research come a to develop  the nursing service

... Show More
Crossref
View Publication Preview PDF
Publication Date
Fri Mar 01 2019
Journal Name
Al-khwarizmi Engineering Journal
The Effect of Micro and Nano Material on Critical Heat Flux (CHF) Enhancement

The Nano materials play a very important role in the heat transfer enhancement. An experimental investigation has been done to understand the behaviors of nano and micro materials on critical heat flux. Pool boiling experiments have used for several concentrations of nano and micro particles on a 0.4 mm diameter nickel chrome (Ni-Cr) wire heater which is heated electrically at atmospheric pressure. Zinc oxide(ZnO) and silica(SiO2) were used as a nano and micro fluids with concentrations (0.01,0.05,0.1,0.3,0.5,1 g/L), a marked enhancement in CHF have been shown in the results for nano and micro fluids for different concentrations compared to distilled water. The deposition of the nano particles on the heater surface was the rea

... Show More
View Publication Preview PDF
Publication Date
Sun Jan 01 2017
Journal Name
Journal Of Telecommunication, Electronic And Computer Engineering
The critical success factors (CSFs) for IT projects

Huge yearly investments were made by organizations for the development and maintenance. However, it has been reported that most of the IT projects fails as it is delayed, over budget and discontinued quality. A systematic literature review (SLR) was conducted to identify the critical success factors (CSFs) for the IT projects. Nine (9) CSFs was identified from the SLR. An online survey was conducted among 103 respondents from developers and IT managers. The data was analyzed using the Statistical Package for Social Science (SPSS 22). The findings showed that the highest CSFs of IT projects is commitment and motivation. Project monitoring was found the lowest score ranked by respondents.

Scopus (13)
Scopus
Publication Date
Thu Feb 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Developing the investment budgeting through evaluation of investment projects

The aim of the research is to determine the impact of evaluating the investment projects in the development and preparation of investment budgets prepared by the economic units, since the investment projects are of an important and vital nature of the economic units, because these projects include the length of time for preparation and implementation and the accompanying period of this risk and uncertainties as well as need To the many funds to complete the project , The process of evaluating the implemented projects, which have been prepared an investment budget previously will contribute to the extent of matching the estimated data with the actual results or deviations, which is a step to avoid these errors in future p

... Show More
Crossref
View Publication Preview PDF
Publication Date
Sun Mar 01 2009
Journal Name
Al-khwarizmi Engineering Journal
Numerical Computations of Transonic Critical Aerodynamic Behavior of a Realistic Artillery Projectile

The determination of aerodynamic coefficients by shell designers is a critical step in the development of any projectile design. Of particular interest is the determination of the aerodynamic coefficients at transonic speeds. It is in this speed regime that the critical aerodynamic behavior occurs and a rapid change in the aerodynamic coefficients is observed. Two-dimensional, transonic, flow field computations over projectiles have been made using Euler equations which were used for solution with no special treatment required. In this work a solution algorithm is based on finite difference MacCormack’s technique for solving mixed subsonic-supersonic flow problem. Details of the asymmetrically located shock waves on the projectiles hav

... Show More
View Publication Preview PDF
Publication Date
Thu Dec 28 2017
Journal Name
Al-khwarizmi Engineering Journal
Aircraft Lateral-Directional Stability in Critical Cases via Lyapunov Exponent Criterion

Based on Lyapunov exponent criterion, the aircraft lateral-directional stability during critical flight cases is presented. A periodic motion or limit cycle oscillation isdisplayed. A candidate mechanism for the wing rock limit cycle is the inertia coupling between an unstable lateral-directional (Dutch roll) mode with stable longitudinal (short period) mode. The coupling mechanism is provided by the nonlinear interaction of motion related terms in the complete set equations of motion. To analyze the state variables of the system, the complete set of nonlinear equations of motion at different high angles of attack are solved. A novel analysis including the variation of roll angle as a function of angle of attack is proposed. Furthermore

... Show More
View Publication Preview PDF