Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security issues, selection of low-price bids, weather factors, and owner failures. Some of these are in line with findings from similar studies in other countries and regions, but some are unique to the Iraqi project sample, such as security issues and low-price bid selection. While many studies have examined factors causing delays and cost overruns, this study offers unique insights into factors that need to be considered when implementing projects for post disaster emergency reconstruction in areas impacted by wars and terrorism.

Scopus Clarivate Crossref
View Publication
Publication Date
Wed Jan 01 2020
Journal Name
International Journal Of Engineering Business Management
Using ANN in emergency reconstruction projects post disaster
...Show More Authors

The purpose of this study is to avoid delays and cost changes that occur in emergency reconstruction projects especially in post disaster circumstances. This study is aimed to identify the factors that affect the real construction period and the real cost of a project against the estimated period of construction and the estimated cost of the project. The case study is related to the construction projects in Iraq. Thirty projects in different areas of construction in Iraq were selected as a sample for this study. Project participants from the projects authorities provided data about the projects through a data collection distributed survey made by the authors. Mathematical data analysis was used to construct a model to predict change

... Show More
View Publication
Scopus (5)
Crossref (7)
Scopus Clarivate Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Ssrn Electronic Journal
Diagnoses of Delay Causes in Construction Projects During Disaster
...Show More Authors

Purpose: The aim of this study was to gain insight into causes of time delays and cost overruns in a selection of thirty case projects in Iraq. Delay factors have been studied in many countries/contexts, but not much data exists from countries under the conditions characterizing Iraq during the last 10-15 years.Design/methodology/approach: A case study approach was adopted, with thirty construction projects selected from the Baghdad region, of different types and sizes. For the case of the study, the participants in the projects provided data about the projects through the data collection tool distributed through the questionnaire directed to them. Statistical data analysis was used to build statistical relationships between time and cost d

... Show More
View Publication
Crossref
Publication Date
Tue Mar 01 2016
Journal Name
Journal Of Engineering
Critical Success Factors in Construction Projects (Governmental Projects as a Case Study)
...Show More Authors

The importance of the construction sector and its Great role in the provision of services and infrastructure, reduce poverty, improve living conditions and improve the economic situation in the country, impose attention to the way in which the projects implemented for its improvement and to get successful projects. The objective of this research was to determine the criteria for success as well as critical success and failure factors that have a significant impact on project success. A selected 75 engineer (department managers, project managers and engineers) are asked to fill  the questionnaire form, Sixty-seven valid questionnaire forms were analyzed statistically to get search results, which were as follows : Twe

... Show More
View Publication Preview PDF
Publication Date
Sat Feb 12 2022
Journal Name
Engineering, Technology & Applied Science Research
Investigating the Causes of Poor Cost Control in Iraqi Construction Projects
...Show More Authors

Controlling cost in construction projects is an essential issue. This study investigates the most critical problems that cause weakness in cost control in Iraqi construction projects. The quantitative technique was used by conducting a survey directed to professionals who work on construction projects. One hundred and sixty-four questionnaire forms were distributed to private sector companies, government companies, and government institutions, and the responses were subjected to the required statistical analysis. The results indicate that the most influential factors are the weakness in keeping up with the use of modern concepts, methods, and technologies, the delay in receiving the amounts due for work done from the owner, fluctuat

... Show More
View Publication
Crossref (6)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of The Mechanical Behavior Of Materials
Identification of the main causes of risks in engineering procurement construction projects
...Show More Authors
Abstract<p>Many risks have adverse consequences for construction projects’ objectives such as quality, schedule, and cost. As engineering procurement construction (EPC) contracts gradually become one of the most common types used in implementing major large-scale construction projects, identifying common risk types and analyzing their root causes is important for developing measures to decrease and eliminate future risks in these types of contracts. The information about the main causes of risks was collected <italic>via</italic> well-structured questionnaires addressed to construction sector professionals and preparing lists of main potential risks in EPC/construction projects throu</p> ... Show More
View Publication
Crossref (1)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Ssrn Electronic Journal
The Prospective of Artificial Neural Network (ANN’s) Model Application to Ameliorate Management of Post Disaster Engineering Projects
...Show More Authors

Currently and under the COVID-19 which is considered as a kind of disaster or even any other natural or manmade disasters, this study was confirmed to be important especially when the society is proceeding to recover and reduce the risks of as possible as injuries. These disasters are leading somehow to paralyze the activities of society as what happened in the period of COVID-19, therefore, more efforts were to be focused for the management of disasters in different ways to reduce their risks such as working from distance or planning solutions digitally and send them to the source of control and hence how most countries overcame this stage of disaster (COVID-19) and collapse. Artificial intelligence should be used when there is no practica

... Show More
View Publication
Crossref (1)
Crossref
Publication Date
Wed Feb 01 2023
Journal Name
Journal Of Engineering
Procurement Management of Power Plants Construction Projects in Iraq
...Show More Authors

The government of Iraq states that despite the massive amounts invested in the power generating sector, the country has been plagued by power outages for more than three decades; One of the most common sources of the problem and significant impact on the waste of public funds in contractual processes. The Ministry of Planning issued the sectorial
specialized standard bidding documents (SSBD) of Design, Supply, and Installation of the Electromechanical Works (DSIoEW), which is primarily designed to support the Ministry of Electricity (MoE) by developing economic projects to improve the contractual process that led to raisings Iraqi electricity generation field. The research evaluates the impact of
applying the SSBD-DSIoEW for

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Sat Apr 01 2017
Journal Name
Journal Of Economics And Administrative Sciences
Risk Analysis of Projects Accordance with the Professional Project Management System: A case- Study Mansur Construction Contracting Company here
...Show More Authors

The research aims to identify the risks faced by projects and work on the administration, such as those risks by using professional Project Management System (Project Management Professional) by identifying those risks and their impact on the objectives of the project, if they occur and to provide appropriate responses to Ha.autam search application on the draft Law Faculty port by the General Mansour Construction Contracting company has been using a method personal interview with the heads of departments and project managers in the Al-Mansour and tools descriptive and quantitative analysis as was used (likelihood and impact of risk analysis, Ai_kaoa scheme Sbb- effect, analysis of probability and impact, risk matrix (probability

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Aug 01 2016
Journal Name
Journal Of Engineering
Performance Evaluation of the Investment Projects during the Implementation Phase (Najaf province as a case study)
...Show More Authors

The construction project is a very complicated work by its nature and requires specialized knowledge to lead it to success. The construction project is complicated socially, technically and economically in its planning, management and implementation aspects due to the fact that it has many variables and multiple stakeholders in addition to being affected by the surrounding environment. Successful projects depend on three fundamental points which are cost-time, performance and specifications. The project stakeholder's objective to achieve best specifications and the cost-time frame stipulated in the contract.

The question is, was the optimum implementation accomplished? The provision for the success of the project

... Show More
View Publication Preview PDF
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of Engineering
Developing Crisis Management System for Construction Projects in Iraq
...Show More Authors

Construction is a complicated process that takes place in an almost uncontrollable environment. Although projects can be carefully planned in advance in principle, there is a chance that unforeseen events and crises can disrupt these plans, affecting project development. Because the initial investment expenditures in construction projects are so large, they may be quickly influenced by crises, resulting in significant financial losses. The 2014 financial crisis was one of the most prominent crises that Iraq faced, which significantly impacted various activities in general and the construction industry in particular. Despite the importance of crisis management systems, the researchers found a great lack of local studies looking at cr