Diagnoses of Delay Causes in Construction Projects During Disaster
...Show More Authors

Purpose: The aim of this study was to gain insight into causes of time delays and cost overruns in a selection of thirty case projects in Iraq. Delay factors have been studied in many countries/contexts, but not much data exists from countries under the conditions characterizing Iraq during the last 10-15 years.Design/methodology/approach: A case study approach was adopted, with thirty construction projects selected from the Baghdad region, of different types and sizes. For the case of the study, the participants in the projects provided data about the projects through the data collection tool distributed through the questionnaire directed to them. Statistical data analysis was used to build statistical relationships between time and cost delay ratios and delay factors.Findings: Major delay factors identified were contractor failures resulting in schedule overruns, re-designs, poor planning and frequent change orders, security issues, low bid selection, weather factors, and owner failures.Originality/value: While many studies have looked into factors causing delays and cost overruns, few have studied projects in conditions such as have dominated Iraq the last decade and a half during pandemic as external factors. As such, this study offers unique insights into factors that need to be taken into account when implementing projects in such a context

Crossref
View Publication
Publication Date
Mon Feb 08 2021
Journal Name
Public Works Management & Policy
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security is

... Show More
View Publication
Scopus (13)
Crossref (17)
Scopus Clarivate Crossref
Publication Date
Mon Oct 02 2023
Journal Name
Journal Of Engineering
Main Delay Factors of Implementation EPC Construction Projects in Iraq
...Show More Authors

This essay aims to highlight the most important issues and difficulties facing implementing large projects that follow the turn-key method, considered one of the types of contractual methods in Iraq, especially for large and complex projects requiring speedy completion. The projects implemented in this way face delays and delays in completion, which led to the lack of benefit from the projects for which they were implemented, especially those affecting the lives of citizens within the health sector. The case study dealt with the construction of hospitals with multi-bed capacities within multiple governorates in Iraq, With large financial allocations within the federal budget of the Government of Iraq over several years.

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Sat Feb 12 2022
Journal Name
Engineering, Technology & Applied Science Research
Investigating the Causes of Poor Cost Control in Iraqi Construction Projects
...Show More Authors

Controlling cost in construction projects is an essential issue. This study investigates the most critical problems that cause weakness in cost control in Iraqi construction projects. The quantitative technique was used by conducting a survey directed to professionals who work on construction projects. One hundred and sixty-four questionnaire forms were distributed to private sector companies, government companies, and government institutions, and the responses were subjected to the required statistical analysis. The results indicate that the most influential factors are the weakness in keeping up with the use of modern concepts, methods, and technologies, the delay in receiving the amounts due for work done from the owner, fluctuat

... Show More
View Publication
Crossref (6)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of The Mechanical Behavior Of Materials
Identification of the main causes of risks in engineering procurement construction projects
...Show More Authors
Abstract<p>Many risks have adverse consequences for construction projects’ objectives such as quality, schedule, and cost. As engineering procurement construction (EPC) contracts gradually become one of the most common types used in implementing major large-scale construction projects, identifying common risk types and analyzing their root causes is important for developing measures to decrease and eliminate future risks in these types of contracts. The information about the main causes of risks was collected <italic>via</italic> well-structured questionnaires addressed to construction sector professionals and preparing lists of main potential risks in EPC/construction projects throu</p> ... Show More
View Publication
Crossref (1)
Crossref
Publication Date
Wed Jan 01 2020
Journal Name
International Journal Of Engineering Business Management
Using ANN in emergency reconstruction projects post disaster
...Show More Authors

The purpose of this study is to avoid delays and cost changes that occur in emergency reconstruction projects especially in post disaster circumstances. This study is aimed to identify the factors that affect the real construction period and the real cost of a project against the estimated period of construction and the estimated cost of the project. The case study is related to the construction projects in Iraq. Thirty projects in different areas of construction in Iraq were selected as a sample for this study. Project participants from the projects authorities provided data about the projects through a data collection distributed survey made by the authors. Mathematical data analysis was used to construct a model to predict change

... Show More
View Publication
Scopus (5)
Crossref (7)
Scopus Clarivate Crossref
Publication Date
Fri Sep 11 2020
Journal Name
Iop Conference Series: Materials Science And Engineering
Application of Nanotechnology in Iraqi Construction Projects
...Show More Authors

View Publication
Scopus (4)
Crossref (3)
Scopus Crossref
Publication Date
Tue Mar 01 2016
Journal Name
Journal Of Engineering
Critical Success Factors in Construction Projects (Governmental Projects as a Case Study)
...Show More Authors

The importance of the construction sector and its Great role in the provision of services and infrastructure, reduce poverty, improve living conditions and improve the economic situation in the country, impose attention to the way in which the projects implemented for its improvement and to get successful projects. The objective of this research was to determine the criteria for success as well as critical success and failure factors that have a significant impact on project success. A selected 75 engineer (department managers, project managers and engineers) are asked to fill  the questionnaire form, Sixty-seven valid questionnaire forms were analyzed statistically to get search results, which were as follows : Twe

... Show More
View Publication Preview PDF
Publication Date
Sat Jan 01 2011
Journal Name
Journal Of Engineering
CONSTRUCTION DELAY ANALYSIS USING DAILY WINDOWS TECHNIQUE
...Show More Authors

Delays occur commonly in construction projects. Assessing the impact of delay is sometimes a contentious
issue. Several delay analysis methods are available but no one method can be universally used over another in
all situations. The selection of the proper analysis method depends upon a variety of factors including
information available, time of analysis, capabilities of the methodology, and time, funds and effort allocated to the analysis. This paper presents computerized schedule analysis programmed that use daily windows analysis method as it recognized one of the most credible methods, and it is one of the few techniques much more likely to be accepted by courts than any other method. A simple case study has been implement

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Sun Jan 01 2012
Journal Name
Conference
Identifying Causes of Variation in Construction Industry Based on Questionnaire
...Show More Authors

Publication Date
Fri Jun 29 2018
Journal Name
Journal Of Engineering
Examining the Values and Principles of Agile Construction Management in Iraqi Construction Projects
...Show More Authors

The avoidance of failure in construction projects is not an easy task, which makes the failure of the construction project to achieve its objectives a major problem experienced by all countries in the world, especially Iraq. Where nearly two-thirds of the construction projects in the world have been suffered by significant problems as an increase in the cost of the project, delay in the specified duration for execution, and stopping the project. Therefore it is required to study and apply new methods for managing the construction project to ensure its success and achieve its objectives. The aim of this study is to study the Agile project management method and its impact on the construction project. In addition, to identi

... Show More
View Publication Preview PDF
Crossref (12)
Crossref