Preferred Language
Articles
/
Whfroo4BVTCNdQwC8lZw
Diagnoses of Delay Causes in Construction Projects During Disaster
...Show More Authors

Purpose: The aim of this study was to gain insight into causes of time delays and cost overruns in a selection of thirty case projects in Iraq. Delay factors have been studied in many countries/contexts, but not much data exists from countries under the conditions characterizing Iraq during the last 10-15 years.Design/methodology/approach: A case study approach was adopted, with thirty construction projects selected from the Baghdad region, of different types and sizes. For the case of the study, the participants in the projects provided data about the projects through the data collection tool distributed through the questionnaire directed to them. Statistical data analysis was used to build statistical relationships between time and cost delay ratios and delay factors.Findings: Major delay factors identified were contractor failures resulting in schedule overruns, re-designs, poor planning and frequent change orders, security issues, low bid selection, weather factors, and owner failures.Originality/value: While many studies have looked into factors causing delays and cost overruns, few have studied projects in conditions such as have dominated Iraq the last decade and a half during pandemic as external factors. As such, this study offers unique insights into factors that need to be taken into account when implementing projects in such a context

Crossref
View Publication
Publication Date
Fri Mar 19 2021
Journal Name
Periodicals Of Engineering And Natural Sciences (pen)
New cost control techniques in mega construction projects
...Show More Authors

View Publication
Scopus (3)
Crossref (1)
Scopus Crossref
Publication Date
Wed Feb 01 2023
Journal Name
Journal Of Engineering
Procurement Management of Power Plants Construction Projects in Iraq
...Show More Authors

The government of Iraq states that despite the massive amounts invested in the power generating sector, the country has been plagued by power outages for more than three decades; One of the most common sources of the problem and significant impact on the waste of public funds in contractual processes. The Ministry of Planning issued the sectorial
specialized standard bidding documents (SSBD) of Design, Supply, and Installation of the Electromechanical Works (DSIoEW), which is primarily designed to support the Ministry of Electricity (MoE) by developing economic projects to improve the contractual process that led to raisings Iraqi electricity generation field. The research evaluates the impact of
applying the SSBD-DSIoEW for

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of Engineering
Developing Crisis Management System for Construction Projects in Iraq
...Show More Authors

Construction is a complicated process that takes place in an almost uncontrollable environment. Although projects can be carefully planned in advance in principle, there is a chance that unforeseen events and crises can disrupt these plans, affecting project development. Because the initial investment expenditures in construction projects are so large, they may be quickly influenced by crises, resulting in significant financial losses. The 2014 financial crisis was one of the most prominent crises that Iraq faced, which significantly impacted various activities in general and the construction industry in particular. Despite the importance of crisis management systems, the researchers found a great lack of local studies looking at cr

... Show More
View Publication
Crossref (6)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of Engineering
Developing Crisis Management System for Construction Projects in Iraq
...Show More Authors

Construction is a complicated process that takes place in an almost uncontrollable environment. Although projects can be carefully planned in advance in principle, there is a chance that unforeseen events and crises can disrupt these plans, affecting project development. Because the initial investment expenditures in construction projects are so large, they may be quickly influenced by crises, resulting in significant financial losses. The 2014 financial crisis was one of the most prominent crises that Iraq faced, which significantly impacted various activities in general and the construction industry in particular. Despite the importance of crisis management systems, the researchers found a great lack of local studies l

... Show More
View Publication Preview PDF
Crossref (6)
Crossref
Publication Date
Fri Apr 01 2016
Journal Name
Journal Of Engineering
A Program Applying Professional Safety Basics in Construction Projects
...Show More Authors

When industrial and  constructional renaissance started in the world, the great interest was going on towards the equipment’s,  which was the first mean for production. After industry was settled the interest was going on towards the men ship which manpower on which the production depends. It was approved that it represents the basic part in all of the processes and the protection of those individuals against dangers of these equipment’s, industry and its accidents was the basic things which was studied in many researches until it crystallized in general principles for all industries and other take care in each industry.

     The professional safety is concerned as restrict which

... Show More
View Publication Preview PDF
Publication Date
Sat Jan 01 2022
Journal Name
Ssrn Electronic Journal
The Prospective of Artificial Neural Network (ANN’s) Model Application to Ameliorate Management of Post Disaster Engineering Projects
...Show More Authors

Currently and under the COVID-19 which is considered as a kind of disaster or even any other natural or manmade disasters, this study was confirmed to be important especially when the society is proceeding to recover and reduce the risks of as possible as injuries. These disasters are leading somehow to paralyze the activities of society as what happened in the period of COVID-19, therefore, more efforts were to be focused for the management of disasters in different ways to reduce their risks such as working from distance or planning solutions digitally and send them to the source of control and hence how most countries overcame this stage of disaster (COVID-19) and collapse. Artificial intelligence should be used when there is no practica

... Show More
View Publication
Crossref (1)
Crossref
Publication Date
Mon Aug 01 2022
Journal Name
Journal Of Engineering
The Causes Influencing the Occurrence of Variation Orders in the Construction of Buildings
...Show More Authors

In the construction of buildings usually, problems occur because of the causes of change orders. The main causer of change orders is the owners, consultants, and contractors. These changes lead to conflicts among them which result in influencing building projects. Therefore, it is necessary to analyze the causes of change orders to reduce them and facilitate management. This paper determines the most critical factors that cause change orders from a different point of view, a consulting owner and a contractor, and a study of the reality of the management of change orders when constructing public buildings. The method employed in this research is a field survey using interviews with experts working in the construction of p

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Wed Jan 01 2020
Journal Name
Periodicals Of Engineering And Natural Sciences
Using modified earned value for cost control in construction projects
...Show More Authors

Scopus (7)
Scopus
Publication Date
Wed Dec 01 2021
Journal Name
Civil And Environmental Engineering
Prediction of the Delay in the Portfolio Construction Using Naïve Bayesian Classification Algorithms
...Show More Authors
Abstract<p>Projects suspensions are between the most insistent tasks confronted by the construction field accredited to the sector’s difficulty and its essential delay risk foundations’ interdependence. Machine learning provides a perfect group of techniques, which can attack those complex systems. The study aimed to recognize and progress a wellorganized predictive data tool to examine and learn from delay sources depend on preceding data of construction projects by using decision trees and naïve Bayesian classification algorithms. An intensive review of available data has been conducted to explore the real reasons and causes of construction project delays. The results show that the postpo</p> ... Show More
Scopus (5)
Crossref (5)
Scopus Clarivate Crossref
Publication Date
Thu Feb 28 2019
Journal Name
Journal Of Engineering
Economic Benefits for the Application of Standards of Sustainability in Construction Projects
...Show More Authors

In this research, that been focused on the most important economic benefits expected when applying the three standards of sustainability in construction projects (economic, environmental and social). Fuzzy AHP, a multi-decision decision-making technique for evaluating construction projects. Which when used we get the speed and accuracy in the results. Using this technique will reduce uncertainties decisions significantly (fuzzy environment), that found in most projects .The results of the data analysis showed  that the economic standards take the greatest relative importance (60%) among the three sustainability standards. Therefore, the implementation of any standards need a cost so the economic benefit of any proje

... Show More
View Publication Preview PDF
Crossref (7)
Crossref