Scheduling Critical Activities of Stochastic Projects Management
...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sun Mar 01 2009
Journal Name
Journal Of Economics And Administrative Sciences
The philosophy of Total Quality Management for the environment
...Show More Authors
The Environmental Management System (EMS) is an important foundation for effective control of the organization's outstanding environmental performance. It applies standards for substantive review and provides a structure and a way to apply it in all aspects of th
... Show More
View Publication Preview PDF
Crossref
Publication Date
Fri Apr 26 2024
Journal Name
Mathematical Modelling Of Engineering Problems
Solving Tri-criteria: Total Completion Time, Total Earliness, and Maximum Tardiness Using Exact and Heuristic Methods on Single-Machine Scheduling Problems
...Show More Authors

View Publication
Scopus (2)
Scopus Crossref
Publication Date
Sun Jan 01 2023
Journal Name
E3s Web Of Conferences
Comparing the Design Alternatives Using Building Information Model (BIM) and Constructability in Iraqi Construction Projects
...Show More Authors

The Iraqi construction industry suffers from many issues that lead to many design errors, clashes, delays and cost overruns. Therefore, applying constructability will prevent these issues from happening, as it has proven its positive effect in different projects around the world. The goal of this paper is to use building information modelling (BIM) to assess the constructability, provide the opportunities for the project stakeholders to choose the best constructable design alternative and find the affection of applying constructability on project cost. The practical side of this research consists of two parts: in the first part, 37 factors are collected from the literature review as factors that effect on constructability. After tha

... Show More
View Publication
Scopus Crossref
Publication Date
Sun Jan 01 2017
Journal Name
Dissertation/thesis
A Model To Evaluate the Online Training for Global Virtual Teams in Global Software Projects
...Show More Authors

Publication Date
Wed Dec 01 2021
Journal Name
Civil And Environmental Engineering
Developing A Mathematical Model for Planning Repetitive Construction Projects By Using Support Vector Machine Technique
...Show More Authors
Abstract<p>Each project management system aims to complete the project within its identified objectives: budget, time, and quality. It is achieving the project within the defined deadline that required careful scheduling, that be attained early. Due to the nature of unique repetitive construction projects, time contingency and project uncertainty are necessary for accurate scheduling. It should be integrated and flexible to accommodate the changes without adversely affecting the construction project’s total completion time. Repetitive planning and scheduling methods are more effective and essential. However, they need continuous development because of the evolution of execution methods, essent</p> ... Show More
View Publication
Crossref (3)
Clarivate Crossref
Publication Date
Sat Dec 02 2023
Journal Name
Journal Of Engineering
Empirical Study for Capturing and Allocating Significant Risk Factors in School Construction Projects in Iraq
...Show More Authors

In Iraq, more than 1031 school projects have been halted due to disputes and claims resulting from financial, contractual, or other issues. This research aims to identify, prioritize, and allocate the most critical risk factors that threaten these projects’ success for the duration (2017-2022). Based on a multi-step methodology developed through systematic literature reviews, realistic case studies, and semi-structured interviews, 47 risk factors were identified. Based on 153 verified responses, the survey reveals that the top-ranked risk factors are corruption and bribery, delaying the payments of the financial dues to the contractors or sub-contractors, absence of risk management strategy, multiple change orders due

... Show More
View Publication Preview PDF
Crossref (3)
Crossref
Publication Date
Mon Aug 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Developing System of Solid Waste Management (Applied Research in Hilla City)
...Show More Authors

Abstract

The research aims to stand on the practice of operations management of solid waste in the city of Hilla, carried out by the mayor of Hilla Directorate - solid and the environment Waste Division, through field visits and personal interview to officials of the municipal departments and units of its data collection and information related to solid waste, and assess the current status of the processes of collection and transport waste through the questionnaire that had been prepared for citizens and employees, the search reach a set of conclusions was the most important, operations carried out by the municipality of Hilla Directorate only limited to two (collection, transportation and disposal of wa

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Jun 19 2023
Journal Name
Journal Of Engineering
Medical waste management in Al-Kut City
...Show More Authors

This research investigates solid waste management in Al-Kut City. It included the collection of medical and general solid waste generated in five hospitals different in their specialization and capacity through one week, starting from 03/02/2012. Samples were  collected and analyzed periodically to find their generation rate, composition, and physical properties. Analysis results indicated that generation rate ranged between (1102 – 212) kg / bed / day, moisture content and density were (19.0 % - 197 kg/ m3) respectively for medical waste and (41%-255 kg/ m3) respectively for general waste. Theoretically, medical solid waste generated in Al-Kut City (like any other city), affected by capacity, number of patients in a day, and hosp

... Show More
View Publication Preview PDF
Crossref
Publication Date
Thu Sep 01 2016
Journal Name
Journal Of Engineering
Evaluation of Maintenance Management in Iraqi Governmental Buildings
...Show More Authors

Impact of buildings in Iraq and other countries on the environment is obvious; this problem began to take scientific and humanitarian dimensions in order to reduce and eliminate this problem. This impact can be seen through the energy, water and raw materials consumed for the establishment, operation and maintenance of these buildings, as well as the emissions of hazardous gases and generations of solid wastes.

This work was conducted to assess the current maintenance managerial practice for the governmental buildings to stand on the main obstacle and extrapolation of measures by means of interviews with experts to determine the effective factors and closed questionnaire to state the features and the need for new

... Show More
View Publication Preview PDF
Publication Date
Sun Jul 01 2018
Journal Name
Journal Of Craniofacial Surgery
Surgical Management of the Recent Orbital War Injury
...Show More Authors

View Publication
Scopus (4)
Crossref (3)
Scopus Clarivate Crossref