Scheduling Critical Activities of Stochastic Projects Management
...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sun Jan 01 2017
Journal Name
Professional Safety
Technology’s role in Safety Management
...Show More Authors

Publication Date
Mon Feb 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Employment of critical success factors in achieving the strategy Entrepreneurship: A field research for my company Oil Products Distribution and Midland Refineries
...Show More Authors

Abstract

        The critical success factors of the means of the most modern in determining the main directions for organizations to achieve competitive advantage. and can be a critical success factors in organizations that overlap in the functional areas of the organization. that successful organizations use these factors to get to the uniqueness and distinction. as the entrance of critical success factors with the capacity Evaluative phase correction because discovery increases the perception of managers of what is important to the organization and using them to get to the Strategic Entrepreneurship. as it begins in terms of permanence of success and

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Nov 17 2025
Journal Name
International Journal Of Environmental Analytical Chemistry
A critical review of precision analytical methods for detecting heavy metals in alcoholic and non-alcoholic beverages
...Show More Authors

View Publication
Scopus (1)
Crossref (1)
Scopus Crossref
Publication Date
Mon Mar 18 2019
Journal Name
Al-khwarizmi Engineering Journal
Best Level of Parameters for a Critical Buckling Load for Circular Thin- Walled Structure Subjected to Bending
...Show More Authors

Circular thin walled structures have wide range of applications. This type of structure is generally exposed to different types of loads, but one of the most important types is a buckling. In this work, the phenomena of buckling was studied by using finite element analysis. The circular thin walled structure in this study is constructed from; cylindrical thin shell strengthen by longitudinal stringers, subjected to pure bending in one plane. In addition, Taguchi method was used to identify the optimum combination set of parameters for enhancement of the critical buckling load value, as well as to investigate the most effective parameter. The parameters that have been analyzed were; cylinder shell thickness, shape of stiffeners section an

... Show More
View Publication Preview PDF
Crossref
Publication Date
Sun Jan 01 2023
Journal Name
E3s Web Of Conferences
Comparing the Design Alternatives Using Building Information Model (BIM) and Constructability in Iraqi Construction Projects
...Show More Authors

The Iraqi construction industry suffers from many issues that lead to many design errors, clashes, delays and cost overruns. Therefore, applying constructability will prevent these issues from happening, as it has proven its positive effect in different projects around the world. The goal of this paper is to use building information modelling (BIM) to assess the constructability, provide the opportunities for the project stakeholders to choose the best constructable design alternative and find the affection of applying constructability on project cost. The practical side of this research consists of two parts: in the first part, 37 factors are collected from the literature review as factors that effect on constructability. After tha

... Show More
View Publication
Scopus Crossref
Publication Date
Sun Jan 01 2017
Journal Name
Dissertation/thesis
A Model To Evaluate the Online Training for Global Virtual Teams in Global Software Projects
...Show More Authors

Publication Date
Wed Dec 01 2021
Journal Name
Civil And Environmental Engineering
Developing A Mathematical Model for Planning Repetitive Construction Projects By Using Support Vector Machine Technique
...Show More Authors
Abstract<p>Each project management system aims to complete the project within its identified objectives: budget, time, and quality. It is achieving the project within the defined deadline that required careful scheduling, that be attained early. Due to the nature of unique repetitive construction projects, time contingency and project uncertainty are necessary for accurate scheduling. It should be integrated and flexible to accommodate the changes without adversely affecting the construction project’s total completion time. Repetitive planning and scheduling methods are more effective and essential. However, they need continuous development because of the evolution of execution methods, essent</p> ... Show More
View Publication
Crossref (7)
Clarivate Crossref
Publication Date
Sat Dec 02 2023
Journal Name
Journal Of Engineering
Empirical Study for Capturing and Allocating Significant Risk Factors in School Construction Projects in Iraq
...Show More Authors

In Iraq, more than 1031 school projects have been halted due to disputes and claims resulting from financial, contractual, or other issues. This research aims to identify, prioritize, and allocate the most critical risk factors that threaten these projects’ success for the duration (2017-2022). Based on a multi-step methodology developed through systematic literature reviews, realistic case studies, and semi-structured interviews, 47 risk factors were identified. Based on 153 verified responses, the survey reveals that the top-ranked risk factors are corruption and bribery, delaying the payments of the financial dues to the contractors or sub-contractors, absence of risk management strategy, multiple change orders due

... Show More
View Publication Preview PDF
Crossref (3)
Crossref
Publication Date
Mon Jun 10 2024
Journal Name
Iraqi Journal For Computer Science And Mathematics
Solving tri-criteria: total completion time, total late work, and maximum earliness by using exact, and heuristic methods on single machine scheduling problem
...Show More Authors

The presented study investigated the scheduling regarding  jobs on a single machine. Each  job will be processed with no interruptions and becomes available for the processing at time 0. The aim is finding a processing order with regard to jobs, minimizing total completion time , total late work , and maximal tardiness  which is an NP-hard problem. In the theoretical part of the present work, the mathematical formula for the examined problem will be presented, and a sub-problem of the original problem of minimizing the multi-objective functions  is introduced. Also, then the importance regarding the dominance rule (DR) that could be applied to the problem to improve good solutions will be shown. While in the practical part, two

... Show More
View Publication
Scopus (4)
Crossref (2)
Scopus Crossref
Publication Date
Sun Dec 01 2019
Journal Name
Baghdad Science Journal
Comparison between Biological Activities of Commercial and Synthesized Carbon Nanotubes by Flame Fragments Deposition Technique
...Show More Authors

Carbon nanotubes (CNTs) were synthesized via liquefied petroleum gas (LPG) as precursor using flame fragments deposition (FFD) technique. In vitro, biological activates of carbon nanotubes (CNTs) synthesized by FFD technique were investigated. The physiochemical characterizations of synthesized CNTs are similar to other synthesized CNTs and to the standard sample. Pharmaceutical application of synthesized CNTs was studied via conjugation and adsorption with different types of medicines as promote groups. The conjugation of CNTs was performed by adsorption the drugs such as sulfamethoxazole (SMX) and trimethoprim (TMP) on CNTs depending on physical properties of both bonded parts. The synthesized CNTs almost have the same performance in a

... Show More
View Publication Preview PDF
Scopus (3)
Crossref (2)
Scopus Clarivate Crossref