Sustainability and recovery project management implementation on construction projects in Iraq
...Show More Authors

Scopus
Publication Date
Mon Feb 08 2021
Journal Name
Public Works Management & Policy
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security is

... Show More
View Publication
Scopus (20)
Crossref (27)
Scopus Clarivate Crossref
Publication Date
Fri Mar 19 2021
Journal Name
Periodicals Of Engineering And Natural Sciences (pen)
New cost control techniques in mega construction projects
...Show More Authors

View Publication
Scopus (5)
Crossref (4)
Scopus Crossref
Publication Date
Sun Apr 11 2021
Journal Name
Environment, Development And Sustainability
Developing a system for assessing the sustainability in school building projects
...Show More Authors

View Publication
Crossref (9)
Clarivate Crossref
Publication Date
Sat Jan 01 2022
Journal Name
International Journal Of Management And Enterprise Development
Studying the decision-making state and impact in Iraqi construction projects
...Show More Authors

View Publication
Scopus (2)
Crossref (1)
Scopus Crossref
Publication Date
Sat Jan 01 2022
Journal Name
International Journal Of Management And Enterprise Development
Studying The Decision-Making State and Impact in Iraqi Construction Projects
...Show More Authors

View Publication
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Archives Of Civil Engineeringthis Link Is Disabled
Factors affecting time and cost trade-off in multiple construction projects
...Show More Authors

Scopus (7)
Scopus
Publication Date
Fri Sep 01 2023
Journal Name
Civil Engineering Journal
Fundamental Challenges and Management Opportunities in Post Disaster Reconstruction Project
...Show More Authors

The study examines the root causes of delays that the project manager is unable to resolve or how the decision-maker can identify the best opportunities to get over these obstacles by considering the project constraints defined as the project triangle (cost, time, and quality) in post-disaster reconstruction projects to review the real challenges to overcome these obstacles. The methodology relied on the exploratory description and qualitative data examined. 43 valid questionnaires were distributed to qualified experienced engineers. A list of 49 factors causes was collected from previous international and local studies. A Relative Important Index (RII) is adapted to determine the level of importance of each sub-criterion in the fou

... Show More
View Publication
Scopus (10)
Crossref (9)
Scopus Clarivate Crossref
Publication Date
Tue Jun 30 2020
Journal Name
Journal Of Planner And Development
Real estate acquisition barrier and its impact on urban development projects" Study Area: Infrastructure project in the capital Baghdad (North East Sewage Line project AL khansaa)
...Show More Authors

The increase the rates of natural growth, urbanization and continuous migration, this has generated constant pressure and, as a result, the capital city of Baghdad faces a number of challenges related to its urban environment, including the challenge of acquiring real estate.

 

 and this research examines the impact of these holdings, representing the main base from which the various projects originate Urban in all areas (economic, social, and recreational).

 

this leads us to the research problem of the obstacles that arise during the process of acquiring real estate to carry out development projects, and to achieve the objectives of research, namely (work to create a regulatory methodology

... Show More
View Publication Preview PDF
Publication Date
Fri Apr 01 2016
Journal Name
Journal Of Engineering
A Program Applying Professional Safety Basics in Construction Projects
...Show More Authors

When industrial and  constructional renaissance started in the world, the great interest was going on towards the equipment’s,  which was the first mean for production. After industry was settled the interest was going on towards the men ship which manpower on which the production depends. It was approved that it represents the basic part in all of the processes and the protection of those individuals against dangers of these equipment’s, industry and its accidents was the basic things which was studied in many researches until it crystallized in general principles for all industries and other take care in each industry.

     The professional safety is concerned as restrict which

... Show More
View Publication Preview PDF
Publication Date
Sat Jan 01 2022
Journal Name
Ssrn Electronic Journal
Diagnoses of Delay Causes in Construction Projects During Disaster
...Show More Authors

Purpose: The aim of this study was to gain insight into causes of time delays and cost overruns in a selection of thirty case projects in Iraq. Delay factors have been studied in many countries/contexts, but not much data exists from countries under the conditions characterizing Iraq during the last 10-15 years.Design/methodology/approach: A case study approach was adopted, with thirty construction projects selected from the Baghdad region, of different types and sizes. For the case of the study, the participants in the projects provided data about the projects through the data collection tool distributed through the questionnaire directed to them. Statistical data analysis was used to build statistical relationships between time and cost d