Risks of Design Stage in Iraqi Construction Project
...Show More Authors

The management of construction projects needs to complete the basics of system management and work. Starting from the idea and how to turn it into a full study and ended at the construction project completion arriving at the purpose prepared for it, so the projects need to control on its operation and integration system in order to succeed.

It is no secret for who concerned in construction projects field that the design stage is a very important stage in construction project because it determines the final features of the project through the requirements provided by the employer for the consultant to formulate it during this phase in the form of plans, drawings, and specifications, then translated on the ground as the shape of completed project meets those requirements.

Therefore it has been necessary to focus in this paper on the design stage also demonstrated and analysis the most important risk facing this stage and their impact on a construction project by introducing a questionnaire to identify the most important risks factors at this stage affecting on the project.

The paper had been shown that the effect of the design stage on Lump sum type of project contract was higher than the unit price, while the most important factor effect on a project its fast response of design team to prepare the design documents in order to facilitate the workflow and sequence of execution with effect level 3.714.

 

 

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sat Nov 03 2018
Journal Name
Iraqi National Journal Of Nursing Specialties
Construction of an Initial Assessment Documentation Tool for Nursing Recording System in Coronary Care Units
...Show More Authors

Objective : The study was carried out to construct an initial assessment documentation tool for nursing
recording system in Coronary Care Unit.
Methodology : A descriptive, purposive sample of (65) nurses was selected from CCU of main
teaching hospitals (Al Karama, Al Kindy, Al Kadimia, Al Yarmmok, Baghdad teaching hospital, Ibn
Al Naffis hospital) and Ibn-Al betar hospital in Baghdad city from the 15th of April 2004 to the 15th of
April 2006.
The instrument was constructed and comprised of two sections: section one included the
nurses' demographic characteristic; section two was the initial assessment documentation tool that
contained (2) parts including: General information form and the initial assessment form.

... Show More
View Publication Preview PDF
Publication Date
Wed Jun 01 2016
Journal Name
Journal Of Engineering
Management Model for Evaluation and Selection of Engineering Equipment Suppliers for Construction Projects in Iraq
...Show More Authors

Engineering equipment is essential part in the construction project and usually manufactured with long lead times, large costs and special engineering requirements. Construction manager targets that equipment to be delivered in the site need date with the right quantity, appropriate cost and required quality, and this entails an efficient supplier can satisfy these targets. Selection of engineering equipment supplier is a crucial managerial process .it requires evaluation of multiple suppliers according to multiple criteria. This process is usually performed manually and based on just limited evaluation criteria, so better alternatives may be neglected. Three stages of survey comprised number of public a

... Show More
View Publication Preview PDF
Publication Date
Mon Feb 08 2021
Journal Name
Public Works Management & Policy
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security is

... Show More
View Publication
Scopus (17)
Crossref (21)
Scopus Clarivate Crossref
Publication Date
Sat Jul 01 2017
Journal Name
Journal Of Construction Engineering And Management
Identification, Quantification, and Classification of Potential Safety Risk for Sustainable Construction in the United States
...Show More Authors

View Publication
Scopus (49)
Crossref (45)
Scopus Clarivate Crossref
Publication Date
Tue May 01 2018
Journal Name
Practice Periodical On Structural Design And Construction
Hazards and Risk in Construction and the Impact of Incentives and Rewards on Safety Outcomes
...Show More Authors

View Publication
Scopus (28)
Crossref (21)
Scopus Clarivate Crossref
Publication Date
Wed Mar 11 2020
Journal Name
Periodicals Of Engineering And Natural Sciences
Applied multivariate analysis of variance in experiment of randomized design
...Show More Authors

The general aim of an experimental design in this paper was to estimate the different treatments effects on the responses by statistical methods. The estimates must be averting biases and the random errors minimized as much as possible. We used multivariate analysis of variance (MANOVA) to analyze design of experiments for several responses. In this paper, we provided three fertilizers (mineral, humic, micro-elements) applied on Yellow Maize experiment. This experiment was conducted by completely randomized design (CRD). We tested four responses (Chlorophyll in paper, total ton / ha, paper area / cm2 and plant height / cm) together to find significant test between them. The partial correlations are between Chlorophyll in paper and total ton

... Show More
View Publication
Scopus (3)
Scopus
Publication Date
Fri May 01 2020
Journal Name
Practice Periodical On Structural Design And Construction
Utilizing Emerging Technologies for Construction Safety Risk Mitigation
...Show More Authors

View Publication
Scopus (102)
Crossref (82)
Scopus Clarivate Crossref
Publication Date
Sun Apr 27 2025
Journal Name
Journal Of Engineering
Construction of a General-Purpose Infrastructure for Rfid – Based Applications
...Show More Authors

View Publication
Publication Date
Mon Apr 09 2018
Journal Name
Al-khwarizmi Engineering Journal
Construction and Evaluation of a Uniaxial Mechanical Actuated Vibration Shaker
...Show More Authors

In the present paper a low cost mechanical vibration shaker of rotating unbalanced type with uniaxial shaking table was designed and constructed in an attempt to provide opportunities for experimental testing and application of vibration in experimental modal analysis, stress relief of weldments, effect of vibration on heat transfer and seismic testing of civil engineering structures. Also, it provides unexpressive solution to enhance the knowledge and technical skills of students in mechanical vibration laboratory. The shaker consists of a five main parts shaker frame, shaker table, flexible support, drive motor, and eccentricity mechanism. The experimental results show that the amplitude of the shaker is increased with increasing the f

... Show More
View Publication Preview PDF
Crossref
Publication Date
Fri Jul 21 2023
Journal Name
Journal Of Engineering
Development of an Integrated Construction Management System for Building Estimation
...Show More Authors

Project management are still depending on manual exchange of information based on paper documents. Where design drawings drafting by computer-aided design (CAD), but the data needed by project management software can not be extracted directly from CAD, and must be manually entered by the user. The process of calculation and collection of information from drawings and enter in the project management software needs effort and time with the possibility of errors in the transfer and enter of information. This research presents an integrated computer system for building projects where the extraction and import quantities, through the interpretation of AutoCAD drawing with MS Access database of unit costs and productivities for the pricing and

... Show More
View Publication Preview PDF
Crossref