Construction Time-Cost Optimization Modeling Using Ant Colony Optimization
...Show More Authors

In the field of construction project management, time and cost are the most important factors to be considered in planning every project, and their relationship is complex. The total cost for each project is the sum of the direct and indirect cost. Direct cost commonly represents labor, materials, equipment, etc.
Indirect cost generally represents overhead cost such as supervision, administration, consultants, and interests. Direct cost grows at an increasing rate as the project time is reduced from its original planned time. However, indirect cost continues for the life of the project and any reduction in project time means a reduction in indirect cost. Therefore, there is a trade-off between the time and cost for completing construction activities.
In this research, modeling of time-cost optimization, generating global optimum solution for time and cost problem, and lowering construction time and cost using ant colony optimization algorithm

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Wed Jun 01 2016
Journal Name
Journal Of Engineering
Application of Total Quality Management (TQM) Requirements in Risk Management in Construction Projects in Iraq
...Show More Authors

Total quality management  considers one of the modern scientific entrances  which practiced by productivity service organizations alike to provide appropriate quality required outputs according to the needs and desires of customers manage , enable the organization seeking to continue and grow in light of the increasing competition from the satisfy and provide the appropriate total quality management requirements whenever led to face risks that they may have  in a manner in which they can be addressed and find ways to avoid them in the future when repeated.                          &n

... Show More
View Publication Preview PDF
Publication Date
Sat Dec 02 2023
Journal Name
Journal Of Engineering
Empirical Study for Capturing and Allocating Significant Risk Factors in School Construction Projects in Iraq
...Show More Authors

In Iraq, more than 1031 school projects have been halted due to disputes and claims resulting from financial, contractual, or other issues. This research aims to identify, prioritize, and allocate the most critical risk factors that threaten these projects’ success for the duration (2017-2022). Based on a multi-step methodology developed through systematic literature reviews, realistic case studies, and semi-structured interviews, 47 risk factors were identified. Based on 153 verified responses, the survey reveals that the top-ranked risk factors are corruption and bribery, delaying the payments of the financial dues to the contractors or sub-contractors, absence of risk management strategy, multiple change orders due

... Show More
View Publication Preview PDF
Scopus (7)
Crossref (3)
Scopus Crossref
Publication Date
Tue May 01 2018
Journal Name
Practice Periodical On Structural Design And Construction
Hazards and Risk in Construction and the Impact of Incentives and Rewards on Safety Outcomes
...Show More Authors

View Publication
Scopus (40)
Crossref (30)
Scopus Clarivate Crossref
Publication Date
Mon Feb 08 2021
Journal Name
Public Works Management & Policy
Causes of Problems in Post-Disaster Emergency Re-Construction Projects—Iraq as a Case Study
...Show More Authors

This study examines the causes of time delays and cost overruns in a selection of thirty post-disaster reconstruction projects in Iraq. Although delay factors have been studied in many countries and contexts, little data exists from countries under the conditions characterizing Iraq during the last 10-15 years. A case study approach was used, with thirty construction projects of different types and sizes selected from the Baghdad region. Project data was gathered from a survey which was used to build statistical relationships between time and cost delay ratios and delay factors in post disaster projects. The most important delay factors identified were contractor failure, redesigning of designs/plans and change orders, security is

... Show More
View Publication
Scopus (32)
Crossref (38)
Scopus Clarivate Crossref
Publication Date
Mon Jan 01 2024
Journal Name
Open Engineering
Experimental investigation of the effect of horizontal construction joints on the behavior of deep beams
...Show More Authors
Abstract<p>Construction joints serve as interruption points in the concrete placement process, which is necessary because it is often not feasible to pour concrete continuously in many structures. The quantity of concrete that can be poured at a single instance depends on the batching and mixing capacity, as well as the strength of the formwork. An effective construction joint must ensure sufficient flexural and shear continuity across the junction. Many studies investigated the construction joints in the reinforced concrete (RC) normal beams, but there are no studies investigating the effect of construction joints on the behavior of the RC deep beams. This study was prepared to show the behavio</p> ... Show More
View Publication
Scopus (3)
Crossref (3)
Scopus Crossref
Publication Date
Sat Jul 01 2017
Journal Name
Journal Of Construction Engineering And Management
Identification, Quantification, and Classification of Potential Safety Risk for Sustainable Construction in the United States
...Show More Authors

View Publication
Scopus (62)
Crossref (59)
Scopus Clarivate Crossref
Publication Date
Sat Aug 01 2015
Journal Name
Journal Of Engineering
A Real-Time Fuzzy Load Flow and Contingency Analysis Based on Gaussian Distribution System
...Show More Authors

Fuzzy logic is used to solve the load flow and contingency analysis problems, so decreasing computing time and its the best selection instead of the traditional methods. The proposed  method is very accurate with outstanding computation time, which made the fuzzy load flow (FLF) suitable for real time application for small- as well as large-scale power systems. In addition that, the FLF efficiently able to solve load flow problem of ill-conditioned power systems and contingency analysis. The FLF method using Gaussian membership function requires less number of iterations and less computing time than that required in the FLF method using triangular membership function. Using sparsity technique for the input Ybus sparse matrix data gi

... Show More
View Publication Preview PDF
Publication Date
Sat Jun 30 2012
Journal Name
Al-kindy College Medical Journal
Prothrombin Time role in Head Injury & Intracranial Hematomas, A prospective Study of 325 cases
...Show More Authors

Objective: Aimed to asses the role of PT estimation in early diagnosis and predicting the extent and the outcome of head injury with ICerH and/ or Contusion
Method :PT was measured by Digiclot 818
Group –1: One hundred consecutive head injured patients admitted at Neurosurgical and Al Ramadi teaching hospitals were initially estimated for prothrombin time and subsequently scanned
Group-2 : Two hundred twenty five consecutive non scanned head injured patients admitted to Neurosurgical and Al Ramadi teaching hospitals were estimated with prothrombin time at the time of insult and subsequently for the next two weeks Al – Kindy Col Med J 2012; Vol. 8 No. 1 P: 54
Clinical and neurological evaluation (GCS) score in addition to

... Show More
View Publication Preview PDF
Publication Date
Mon Mar 13 2017
Journal Name
Journal Of Baghdad College Of Dentistry
White Spot Lesions Among Patients Treated With Fixed Orthodontic Appliance at Different Time Intervals
...Show More Authors

ABSTRACT Background:- White spot lesions are common esthetic problem that compromise the success of orthodontic treatment. This study aimed to assess white spot lesions in patients with fixed orthodontic appliance at different time intervals. Materials & Methods:- Thirty two patients (24 females and 8 males) were included in this study and they underwent clinical examination for white spot lesions using enamel decalcification index at four time intervals: (2-3 weeks after appliance insertion, 2, 4 and 6 months). Results:- The patients were free of white spot lesions at the appliance insertion visit. The mean of white spot lesions was 2.22 which were increased significantly during six months to reach 24.59 at the end of study. There was a si

... Show More
View Publication Preview PDF
Crossref (5)
Crossref
Publication Date
Mon May 01 2023
Journal Name
Periodicals Of Engineering And Natural Sciences
Solving the multi-criteria: total completion time, total late work, and maximum earliness problem
...Show More Authors

Within this research, The problem of scheduling jobs on a single machine is the subject of study to minimize the multi-criteria and multi-objective functions. The first problem, minimizing the multi-criteria, which include Total Completion Time, Total Late Work, and Maximum Earliness Time (∑𝐶𝑗, ∑𝑉𝑗, 𝐸𝑚𝑎𝑥), and the second problem, minimizing the multi-objective functions ∑𝐶𝑗 + ∑𝑉𝑗 +𝐸𝑚𝑎𝑥 are the problems at hand in this paper. In this study, a mathematical model is created to address the research problems, and some rules provide efficient (optimal) solutions to these problems. It has also been proven that each optimal solution for ∑𝐶𝑗 + ∑𝑉𝑗 + 𝐸𝑚𝑎𝑥 is an effic

... Show More
View Publication
Scopus (7)
Crossref (1)
Scopus Crossref