Construction Time-Cost Optimization Modeling Using Ant Colony Optimization
...Show More Authors

In the field of construction project management, time and cost are the most important factors to be considered in planning every project, and their relationship is complex. The total cost for each project is the sum of the direct and indirect cost. Direct cost commonly represents labor, materials, equipment, etc.
Indirect cost generally represents overhead cost such as supervision, administration, consultants, and interests. Direct cost grows at an increasing rate as the project time is reduced from its original planned time. However, indirect cost continues for the life of the project and any reduction in project time means a reduction in indirect cost. Therefore, there is a trade-off between the time and cost for completing construction activities.
In this research, modeling of time-cost optimization, generating global optimum solution for time and cost problem, and lowering construction time and cost using ant colony optimization algorithm

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sat Dec 30 2017
Journal Name
Al-khwarizmi Engineering Journal
Low Cost Hardware Back Propagation Algorithm
...Show More Authors

The first successful implementation of Artificial Neural Networks (ANNs) was published a little over a decade ago. It is time to review the progress that has been made in this research area. This paper provides taxonomy for classifying Field Programmable Gate Arrays (FPGAs) implementation of ANNs. Different implementation techniques and design issues are discussed, such as obtaining a suitable activation function and numerical truncation technique trade-off, the improvement of the learning algorithm to reduce the cost of neuron and in result the total cost and the total speed of the complete ANN. Finally, the implementation of a complete very fast circuit for the pattern of English Digit Numbers NN has four layers of 70 nodes (neurons) o

... Show More
View Publication Preview PDF
Publication Date
Thu Jun 01 2023
Journal Name
Partial Differential Equations In Applied Mathematics
Determination of time-dependent coefficient in time fractional heat equation
...Show More Authors

View Publication
Scopus (14)
Crossref (3)
Scopus Crossref
Publication Date
Sun Jan 01 2023
Journal Name
E3s Web Of Conferences
Comparing the Design Alternatives Using Building Information Model (BIM) and Constructability in Iraqi Construction Projects
...Show More Authors

The Iraqi construction industry suffers from many issues that lead to many design errors, clashes, delays and cost overruns. Therefore, applying constructability will prevent these issues from happening, as it has proven its positive effect in different projects around the world. The goal of this paper is to use building information modelling (BIM) to assess the constructability, provide the opportunities for the project stakeholders to choose the best constructable design alternative and find the affection of applying constructability on project cost. The practical side of this research consists of two parts: in the first part, 37 factors are collected from the literature review as factors that effect on constructability. After tha

... Show More
View Publication
Scopus Crossref
Publication Date
Sat Jun 27 2020
Journal Name
Asian Journal Of Civil Engineering
Using measured mile method to quantify the loss of labor productivity in Iraqi construction site
...Show More Authors

View Publication
Scopus (5)
Crossref (5)
Scopus Crossref
Publication Date
Mon Jun 01 2015
Journal Name
Conference: 8th International Conference And Exhibition On Design And Production Of Machines And Dies/molds
Design, Construction, and Controlling of A Shaped Metal Deposition Machine Using Arc Metal-Wire System
...Show More Authors

Publication Date
Wed Dec 01 2021
Journal Name
Civil And Environmental Engineering
Developing A Mathematical Model for Planning Repetitive Construction Projects By Using Support Vector Machine Technique
...Show More Authors
Abstract<p>Each project management system aims to complete the project within its identified objectives: budget, time, and quality. It is achieving the project within the defined deadline that required careful scheduling, that be attained early. Due to the nature of unique repetitive construction projects, time contingency and project uncertainty are necessary for accurate scheduling. It should be integrated and flexible to accommodate the changes without adversely affecting the construction project’s total completion time. Repetitive planning and scheduling methods are more effective and essential. However, they need continuous development because of the evolution of execution methods, essent</p> ... Show More
View Publication
Crossref (7)
Clarivate Crossref
Publication Date
Thu Feb 01 2024
Journal Name
Journal Of Engineering
Evaluating the Knowledge for Integrating RM and VM Using BIM in the Iraqi Construction Sector
...Show More Authors

The construction industry plays a crucial role in the countries' economy, especially in the developed country. This point encourages the concerned institution to use new techniques and integrate many techniques and methods to maximize the benefits. The main objective of this research is to evaluate the use of risk management, value management, and building information modeling in the Iraqi construction industry. The evaluation process aims at two objectives. The direct objective was to evaluate the knowledge in risk management (RM), value management (VM), and building information modeling (BIM). The indirect objective was to support the participants with information related to the main items mentioned. The questionnaire

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Tue Dec 01 2009
Journal Name
Iraqi Journal Of Physics
Construction of Anisotype CdS/Si Heterojunction and Lineup Using I-V and C-V Measurements
...Show More Authors

Near-ideal p-CdS/n-Si heterojunction band edge lineup has been investigated for the first time with aid of I-V and C-V measurements. The heterojunction was manufactured by deposition of CdS films prepared by chemical spray pyrolysis technique (CSP) on monocrystalline n-type silicon. The experimental data of the conduction band offset Ec and valence band offset Ec were compared with theoretical values. The band offset Ec=530meV and Ev=770meV obtained at 300K. The energy band diagram of p-CdS/n-Si HJ was constructed. C-V measurements depict that the junction was an abrupt type and the built-in voltage was determined from C-2-V plot

View Publication Preview PDF
Publication Date
Thu Jun 01 2023
Journal Name
Baghdad Science Journal
Design and construction of anair pollution detection system using a laser beam and absorption spectroscopy
...Show More Authors

Air pollution is one of the important problems facing Iraq. Air pollution is the result of uncontrolled emissions from factories, car exhaust electric generators, and oil refineries and often reaches unacceptable limits by international standards. These pollutants can greatly affect human health and regular population activities. For this reason, there is an urgent need for effective devices to monitor the molecular concentration of air pollutants in cities and urban areas. In this research, an optical system has been built consisting of aHelium-Neonlaser,5mWand at 632.8 nm, a glass cell with a defined size, and a power meter(Gentec-E-model: uno) where a scattering of the laser beam occurs due to air pollution. Two pollutants were examin

... Show More
View Publication Preview PDF
Scopus (7)
Crossref (1)
Scopus Crossref
Publication Date
Sun Dec 01 2013
Journal Name
Journal Of Economics And Administrative Sciences
Using Time Series Methods To Modify The Seasonal Variations in the Consumer Price Index
...Show More Authors

     As is  known that the consumer price index (CPI) is one of the most important  price indices because of its direct effect on the welfare of the individual and his living.

       We have been address the problem of Strongly  seasonal  commodities in calculating  (CPI) and identifying some of the solution.

   We have  used an actual data  for a set of commodities (including strongly seasonal commodities) to calculate the index price by using (Annual Basket With Carry Forward Prices method) . Although this method can be successfully used in the context of seasonal&nbs

... Show More
View Publication Preview PDF
Crossref