Scheduling Critical Activities of Stochastic Projects Management
...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Fri Jun 01 2012
Journal Name
Journal Of Economics And Administrative Sciences
The Effect of the Stability of Some Commodity Activities in Iraq on the Estimation of the Statistical Data Models for the Period (1988-2000)
...Show More Authors

There is an assumption implicit but fundamental theory behind the decline by the time series used in the estimate, namely that the time series has a sleep feature Stationary or the language of Engle Gernger chains are integrated level zero, which indicated by I (0). It is well known, for example, tables of t-statistic is designed primarily to deal with the results of the regression that uses static strings. This assumption has been previously treated as an axiom the mid-seventies, where researchers are conducting studies of applied without taking into account the properties of time series used prior to the assessment, was to accept the results of these tests Bmanueh and delivery capabilities based on the applicability of the theo

... Show More
View Publication Preview PDF
Crossref
Publication Date
Tue Dec 31 2019
Journal Name
Journal Of Economics And Administrative Sciences
The Causes and Effects of Earnings Management on Stock Prices
...Show More Authors

This study uses the performance of the discretionary estimation models by using a sample of listed companies in the Netherlands and Germany. The actual accounting framework provides a wide opportunity for managers to influence data in financial reporting. The corporate reporting strategy, the way managers use their discretionary accounting, has a significant effect on the company's financial reporting. The authors contribute to the literature through enhancement to these models to accomplish better effects of identifying earnings management as well as to present evidence that is particular to the Dutch and German setting.

For this, we followed the methodology of Dechow, Sloan, and Sweeney (1995) and Chan

... Show More
View Publication Preview PDF
Crossref (4)
Crossref
Publication Date
Fri Mar 31 2017
Journal Name
Al-khwarizmi Engineering Journal
Design and Implementation of a Pharmaceutical Inventory Database Management System
...Show More Authors

The main aim of this paper are the design and implementation of a pharmaceutical inventory database management system. The system was implemented by creating a database containing information about the stored medicines in the inventory, customers making transactions with the pharmaceutical trading company (which owns the inventory), medical suppliers, employees, payments, etc. The database was connected to the main application using C sharp. The proposed system should help in manag inginventory operations which include adding/updating employees’ information, preparing sale and purchase invoices, generating reports, adding/updating customers and suppliers, tracking customer payments and checking expired medicines in order to be disposed

... Show More
View Publication Preview PDF
Crossref
Publication Date
Tue Apr 01 2025
Journal Name
Journal Of Economics And Administrative Sciences
Evaluation of Knowledge Management System Requirements According to ISO 30401
...Show More Authors

This Paper assesses the knowledge management system (KMS) requirements at Al-Ameed University concerning ISO 30401:2022. Specifically, the research aims to ascertain the degree to which international standards have been complied with and gaps that have been identified. A case study was conducted using field observations, interviews, and checklists to assess the institution's compliance with the KMS framework. The level of implementation and documentation of knowledge management processes was assessed using a seven-point scale. The findings reveal that Al-Ameed University has severe gaps in knowledge creation, sharing, and support for knowledge management in terms of strategic leadership. While certain elements like availability of r

... Show More
View Publication
Crossref
Publication Date
Fri Jul 21 2023
Journal Name
Journal Of Engineering
Development of an Integrated Construction Management System for Building Estimation
...Show More Authors

Project management are still depending on manual exchange of information based on paper documents. Where design drawings drafting by computer-aided design (CAD), but the data needed by project management software can not be extracted directly from CAD, and must be manually entered by the user. The process of calculation and collection of information from drawings and enter in the project management software needs effort and time with the possibility of errors in the transfer and enter of information. This research presents an integrated computer system for building projects where the extraction and import quantities, through the interpretation of AutoCAD drawing with MS Access database of unit costs and productivities for the pricing and

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Aug 04 2025
Journal Name
Journal Of College Of Law For Legal And Political Sciences
Management's responsibility for breach of investment administrative contracts
...Show More Authors

View Publication
Publication Date
Tue Feb 28 2017
Journal Name
Journal Of Engineering
The Impact of Urban Solid Waste Management on Urban Environment
...Show More Authors

The growing population and the rising standard of living in cities as well as the increased commercial, industrial and agricultural activities around the world led to
massive production of waste containing different materials and one of them is the municipal solid waste (MSW), so there is a major problem facing the cities around the world about the waste, how to collect, transfer it and how to discard it. Because the accumulation of wastes, whether in the city alleys or in its squares and especially in its residential areas affect the health of their populations besides this situation will be a major indication of the deteriorating quality of life in the city, as hygiene considered a fundamental criterion for the city beauty as well

... Show More
View Publication Preview PDF
Publication Date
Mon Jan 13 2020
Journal Name
International Journal Of Productivity And Performance Management
An examination of talent management processes in Australian higher education
...Show More Authors
Purpose

The purpose of this paper is to understand the best processes that are currently used in managing talent in Australian higher education (HE) and to examine the policies in terms of talent management processes (TMPs) that are derived from objective one. Pragmatic benefits for academic institutions focused on enhancing talent.

Design/methodology/approach

This study selects the mixed method as its research design. In the qualitative study, there were three methods: brainstorming, focus group and individual interviews, followed by the quantitative questionnaire

... Show More
View Publication
Scopus (22)
Crossref (16)
Scopus Clarivate Crossref
Publication Date
Sat Oct 01 2022
Journal Name
The Egyptian Journal Of Hospital Medicine
Developing Gold-Resveratrol Nanoconjugates for Management of Rheumatoid Arthritis (RA)
...Show More Authors

View Publication
Scopus (3)
Crossref (3)
Scopus Crossref
Publication Date
Fri Jan 01 2021
Journal Name
Review Of International Geographical Education Online
Role of ERP Systems in Improving Human Resources Management Processes
...Show More Authors

This study investigates the role of Enterprise Resources Planning (ERP) systems in improving human resources management (HRM) processes. The rapid environmental changes led to increased demand on the ERP systems, which have changed the manual effort to technology-based processes, providing solutions focusing on the integration of all departments to achieve goals for the entire organization. HRM processes are mainly made up of two classes: strategic and operational HRM. An ERP system works to integrate both of them, making HRM processes more efficient, effective and feasible to provide support to the organization as a whole (inside and outside). In this article, a modest framework is proposed to describe HRM process integrity in relation to

... Show More
Scopus (5)
Scopus