Scheduling Critical Activities of Stochastic Projects Management
...Show More Authors

In this paper, we consider the problem of stochastic project network when some or all activities are interrupted. An approach has been built to schedule the critical activities, by constructing some expressions based on the project lateness costs due to the interruption activities. Two simple example are presented to validate our approach.

Key words: Project Management, Project scheduling, Stochastic activity duration, Stochastic PERT.    

Introduction

   Recently, Projects planning and optimal timing, under uncertainty are extremely critical for many organizations, see [19]. Having an effective mathematical model will give project managers a significant tool for replanning projects allocation decisions in response events and outcomes. As a result, the uncertainty associated with such risky projects should be reduced.     

  No one factor can account for, or prevent, failure in a project. It is common practice for a project team to develop a comprehensive risk assessment and risk management plan. Identifying the most critical activities with regard to schedule risk is a problem faced by all project managers.

  The problem of identifying critical activities (CA) in a deterministic network is well understood, by standard Critical Path Method (CPM) known as Program Evaluation and Review Technique (PERT). Since a project could be delayed if these activities were not completed in the scheduled time. The classical PERT method is the probably is the best-known mechanism for considering the stochastic nature of activity durations, in which it is possible to develop estimates of the uncertainty of the project make span. For more details see [8] & [10 ].

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sun Aug 30 2020
Journal Name
Journal Of Economics And Administrative Sciences
Evaluation of Internal Control Activities and their Role in Administrative Decisions
...Show More Authors

The current research aims to verify the relationship and impact of internal control activities as an independent variable in its dimensions (efficiency, training, independence) in making administrative decisions as a responsive variable and its dimensions (identifying and diagnosing the problem, searching for alternatives, evaluating alternatives, choosing the appropriate alternative, implementing the decision, following up Decision and evaluation) in the Kirkuk Water Directorate, as well as to identify the levels of their practices, and then try to come up with a number of recommendations contribute to the strengthening of internal control activities and the process of making administrative decisions of the researched Directorat

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Oct 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Evaluate the implementation of the investment plan projects A study on the field of the plan projects for the period 2013-2016
...Show More Authors

The main problem of this research is the delay of implementation of the investment plan projects for the period (2013-2016) and the weakness of the staff ability in the ministries and they don’t have the sufficient experience to carry out the implementation process.

Therefore, the research aims to evaluate the implementation of programs and projects of the investment plan in a manner consistent with the objectives set for them without any wasteful of efforts, time and money. And then identify the problems and obstacles to determine the deviations of the implementation of the specific for each sector according to the criteria of evaluation and the form of cost, quality, time and implementation.<

... Show More
View Publication Preview PDF
Crossref
Publication Date
Mon Dec 21 2020
Journal Name
2020 Emerging Technology In Computing, Communication And Electronics (etcce)
An Integrated Grey Wolf Optimizer with Nelder-Mead Method for Workflow Scheduling Problem
...Show More Authors

View Publication
Scopus (1)
Scopus Crossref
Publication Date
Sat Aug 12 2017
Journal Name
Journal Of Engineering
Regulations Enforcement Mechanisms for Sustainable Housing Projects
...Show More Authors


 

View Publication Preview PDF
Publication Date
Sat Aug 01 2020
Journal Name
Iop Conference Series: Materials Science And Engineering
Developing Systems Engineering for Sustainable Infrastructure Projects
...Show More Authors
Abstract<p>Globally, Sustainability is very quickly becoming a fundamental requirement of the construction industry as it delivers its projects; whether buildings or infrastructures. Throughout more than two decades, many modeling schemes, evaluation tools, and rating systems have been introduced en route to realizing sustainable construction. Many of these, however, lack consensus on evaluation criteria, a robust scientific model that captures the logic behind their sustainability performance evaluation, and therefore experience discrepancies between rated results and actual performance. Moreover, very few of the evaluation tools available satisfactorily address infrastructure projects. The res</p> ... Show More
View Publication
Scopus (4)
Crossref (3)
Scopus Crossref
Publication Date
Wed Sep 28 2022
Journal Name
Journal Of The College Of Education For Women
Women's Rape in Iraq between Legislation and Social Norms: A Critical Discourse Analysis
...Show More Authors

Recently, women's rape has been a pervasive problem in the Iraqi society. Thus, it has become necessary to consider the role of language and its influence on the common beliefs and opinions about rape in the Iraqi society. Thus, taking into consideration the critical role of language and its impact on the perception of human reality and the social development based on people's beliefs and principles of life has become highly indispensable. Therefore. The aim of this article is to address this problem critically from legislation and social norms in NGOs' reports (2015; 2019) with reference to some provisions from the Iraqi Panel Code (1969; 2010). Therefore, the researchers examine the discursive strategies and ideological viewpoints in t

... Show More
View Publication Preview PDF
Crossref
Publication Date
Fri Jun 01 2018
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Employment cost management tools in the fast-track method Of the constructionindustries for the purpose of rationalizing costs: An applied research in the Shatt al-Diwaniya transference project General Authority for projects of irrigation and reclamation
...Show More Authors

The important factor in the success of construction projects is its ability to objective estimate of the cost of the project and adapt to the changes of the external environment, which is affected by a lot of elements and the requirements of the competitive environment. The faces of those projects are several problems in order to achieve particular goals. To overcome these difficulties has been the development of research in the last two decades and turn the focus on the role of the cost of project management, by providing information and assist management in planning and control of the budget among the main elements of the project, namely, (time-cost-quality),The research aims at the possibility of developing and implementing mechanisms

... Show More
View Publication Preview PDF
Crossref
Publication Date
Tue Nov 13 2012
Journal Name
Wireless Personal Communications
Design and Implementation of a Scalable RFID-Based Attendance System with an Intelligent Scheduling Technique
...Show More Authors

View Publication
Scopus (17)
Crossref (7)
Scopus Clarivate Crossref
Publication Date
Wed Dec 30 2015
Journal Name
College Of Islamic Sciences
Bashar bin cold language poetic in critical discourse Modern Literary
...Show More Authors

Bashar bin cold language poetic in critical discourse
Modern Literary

View Publication Preview PDF
Publication Date
Mon Aug 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
The Development of the Suez Canal and Projects Competitors
...Show More Authors

The area around the Suez Canal has been chosen particularly  Sinai  to implement the new Suez Canal project parallel to the original 72-km-long channel due to the importance of the commercial site of the Arab Republic of Egypt, competing with shipping lanes, to accommodate the increasing maritime traffic  passing through the Suez canal, and to provide special services for trade world and reduce the economic cost of marine trip. The establishment of six tunnels for automobile and railway transport to Sinai The cost of the establishment of this new channel  and the establishment of the tunnels about (2.8) billion, of which 4 billion cost of the new channel. Project implementation period is one year. The new proj

... Show More
View Publication Preview PDF
Crossref