Abstract
This study was to demonstrate the role-use planning scientific methods is disabled and little used in the planning and follow-up construction of vital projects in the province of Baghdad, including network planning methods, in order to find the optimal time to finish the project in light of the resources available and the budget set for it, in the current research has been used the most prominent network planning methods and two stylistic (CPM / PERT), was the application of the critical path method on standard-design school project (traditional) to draw Action Network according to confirmed times for the activities of the project and account his Crashing time , It was Pert technique applied to the project hemato