Risks of Design Stage in Iraqi Construction Project
...Show More Authors

The management of construction projects needs to complete the basics of system management and work. Starting from the idea and how to turn it into a full study and ended at the construction project completion arriving at the purpose prepared for it, so the projects need to control on its operation and integration system in order to succeed.

It is no secret for who concerned in construction projects field that the design stage is a very important stage in construction project because it determines the final features of the project through the requirements provided by the employer for the consultant to formulate it during this phase in the form of plans, drawings, and specifications, then translated on the ground as the shape of completed project meets those requirements.

Therefore it has been necessary to focus in this paper on the design stage also demonstrated and analysis the most important risk facing this stage and their impact on a construction project by introducing a questionnaire to identify the most important risks factors at this stage affecting on the project.

The paper had been shown that the effect of the design stage on Lump sum type of project contract was higher than the unit price, while the most important factor effect on a project its fast response of design team to prepare the design documents in order to facilitate the workflow and sequence of execution with effect level 3.714.

 

 

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sat Oct 01 2011
Journal Name
Journal Of Engineering
IMPLEMENTATION OF GYPSEOUS SOIL-ASPHALT STABILIZATION TECHNIQUE FOR BASE COURSE CONSTRUCTION
...Show More Authors

The aim of this research work is to study the effect of stabilizing gypseous soil, which covers
vast areas in the middle, west and south parts of Iraq, using liquid asphalt on its strength properties
to be used as a base course layer replacing the traditional materials of coarse aggregate and broken
stones which are scarce at economical prices and hauling distances.
Gypseous soil brought from Al-Ramadi City, west of Iraq, with gypsum content of 66.65%,
medium curing cutback asphalt (MC-30), and hydrated lime are used in this study.
The conducted tests on untreated and treated gypseous soil with different percentages of medium
curing cutback asphalt (MC-30), water, and lime were: unconfined compression strength, and o

... Show More
View Publication Preview PDF
Crossref (3)
Crossref
Publication Date
Wed Nov 02 2011
Journal Name
Journal Of Engineering
Implementation of Gypseous Soil-asphalt Stabilization Technique for Base Course Construction
...Show More Authors

The aim of this research work is to study the effect of stabilizing gypseous soil, which covers vast areas in the middle, west and south parts of Iraq, using liquid asphalt on its strength properties to be used as a base course layer replacing the traditional materials of coarse aggregate and broken stones which are scarce at economical prices and hauling distances. Gypseous soil brought from Al-Ramadi City, west of Iraq, with gypsum content of 66.65%, medium curing cutback asphalt (MC-30), and hydrated lime are used in this study. The conducted tests on untreated and treated gypseous soil with different percentages of medium curing cutback asphalt (MC-30), water, and lime were: unconfined compression strength, and one dimensional confine

... Show More
Publication Date
Mon Jun 01 2015
Journal Name
Journal Of Engineering
Construction of Graduation Certificate Issuing System Based on Digital Signature Technique
...Show More Authors

With the development of computer architecture and its technologies in recent years, applications like e-commerce, e-government, e-governance and e-finance are widely used, and they act as active research areas. In addition, in order to increase the quality and quantity of the ordinary everyday transactions, it is desired to migrate from the paper-based environment to a digital-based computerized environment. Such migration increases efficiency, saves time, eliminates paperwork, increases safety and reduces the cost in an organization. Digital signatures are playing an essential role in many electronic and automatic based systems and facilitate this migration. The digital signatures are used to provide many services and s

... Show More
View Publication Preview PDF
Publication Date
Sun Mar 07 2010
Journal Name
Baghdad Science Journal
Construction of Phenytoin Selective Electrodes and Its Application to Pharmaceutical Preparation
...Show More Authors

Phenytoin selective electrodes were constructed based on penytoin-phosphotungstate (Ph-PT) complex with different plasticizers; di-butyl phosphate (DBP), tri-butyl phosphate (TBP), di-butyl phthalate (DBPH),and o-nitro phenyl octyl ether (NPOE) phthalate. The electrodes based on DBPH, ONPOE plasticizers gave Narnistain slope which are, 56.4 and 55.3mV/decade with detection limit of 1.9x10-5 M , 1.8x10-5 and concentration range 10-1 to 10-4 M and pH range 3.0 – 8.0. The electrodes based on TBP and DBP showed non-Nernistain slopes, 40.2,40.5 mV/decade for both plasticizers. Interfering of some cations was investigated and shows no interfering with electrodes response. Potentiometric methods were used for measuring phenytion in

... Show More
View Publication Preview PDF
Crossref
Publication Date
Tue Dec 22 2020
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Cost Management of construction industries according to the fast-track method
...Show More Authors

Construction projects have become a changing dramatically in recent decades and that the goal of the beneficiaries of the implementation of structural project is to complete the work with less time and within the cost of the specific and the best possible quality may sometimes happen that highlights the importance of time on the rest of the items at the implementation of projects for various reasons, including the need to use the project as soon as possible possible change rapidly to customer's requests, but the high cost of the project represents the biggest obstacle for entrepreneurs with its effects on the quality and the time workers, and is a measure of those elements in monetary terms is the key to integration between them, so the

... Show More
View Publication Preview PDF
Publication Date
Wed Aug 02 2017
Journal Name
International Journal Of Materials Chemistry And Physics
Assessing the Sustainability of Asphalt Stabilized Subgrade Soil for Embankment Construction
...Show More Authors

Gypseous soil is considered as a problematic soil for embankment construction, however, implementation of emulsified asphalt as a stabilization agent could be a proper solution for enhancing its properties as a subgrade soil. In this work, the sustainability of asphalt stabilized soil has been assessed in terms of its resistance to cyclic (freezing-thawing) and (heating-cooling) processes. Specimens have been prepared at optimum fluid content (moisture and emulsion) and tested under direct shear stresses while subjected to 30 cycles of (freezing-thawing) and (heating-cooling). Both of dry and soaked testing conditions have been implemented. Data have been observed after each 10 cycles, and compared with that of reference mix. It was conclud

... Show More
Publication Date
Tue Aug 01 2023
Journal Name
Journal Of Engineering
An Extensive Literature Review on Risk Assessment Models (Techniques and Methodology) for Construction Industry
...Show More Authors

This study looks into the many methods that are used in the risk assessment procedure that is used in the construction industry nowadays. As a result of the slow adoption of novel assessment methods, professionals frequently resort to strategies that have previously been validated as being successful. When it comes to risk assessment, having a precise analytical tool that uses the cost of risk as a measurement and draws on the knowledge of professionals could potentially assist bridge the gap between theory and practice. This step will examine relevant literature, sort articles according to their published year, and identify domains and qualities. Consequently, the most significant findings have been presented in a manne

... Show More
View Publication Preview PDF
Crossref (4)
Crossref
Publication Date
Wed Dec 30 2020
Journal Name
Journal Of Planner And Development
The proportionality of decision taken to sign the AL-Ayadi residential investment project within the Hittin neighborhood in Baghdad by Urban filling style
...Show More Authors

This research will deal in a simple way with the concept of urban expansion and taking the decision to sign the spatial signature of residential investment projects in order to reach through them in a real way to the extent of the proportionality of the decision taken, in light of the fulfillment of the conditions that must be met in the matter of making the decision of the spatial signature of the residential investment project and the extent of commitment to them, in which the conditions are: (Ease of access to services and transportation, adequacy of services, commitment to urban land uses) when establishing the investment project represented by the Al-Ayad residential project in the Hittin neighborhood of Al

... Show More
View Publication Preview PDF
Publication Date
Sun Mar 30 2014
Journal Name
Iraqi Journal Of Chemical And Petroleum Engineering
Design of Horizontal Well Program for Ajeel Field
...Show More Authors

Horizontal wells are of great interest to the petroleum industry today because they provide an attractive means for improving both production rate and recovery efficiency. The great improvements in drilling technology make it possible to drill horizontal wells with complex trajectories and extended for significant depths.
The aim of this paper is to present the design aspects of horizontal well. Well design aspects include selection of bit and casing sizes, detection of setting depths and drilling fluid density, casing, hydraulics, well profile, and construction of drillstring simulator. An Iraqi oil field (Ajeel field) is selected for designing horizontal well to increase the productivity. Short radius horizontal well is suggested fo

... Show More
View Publication Preview PDF
Publication Date
Wed Apr 05 2023
Journal Name
Journal Of Engineering
Construction Time-Cost Optimization Modeling Using Ant Colony Optimization
...Show More Authors

In the field of construction project management, time and cost are the most important factors to be considered in planning every project, and their relationship is complex. The total cost for each project is the sum of the direct and indirect cost. Direct cost commonly represents labor, materials, equipment, etc.
Indirect cost generally represents overhead cost such as supervision, administration, consultants, and interests. Direct cost grows at an increasing rate as the project time is reduced from its original planned time. However, indirect cost continues for the life of the project and any reduction in project time means a reduction in indirect cost. Therefore, there is a trade-off between the time and cost for completing construc