CONSTRUCTION DELAY ANALYSIS USING DAILY WINDOWS TECHNIQUE
...Show More Authors

Delays occur commonly in construction projects. Assessing the impact of delay is sometimes a contentious
issue. Several delay analysis methods are available but no one method can be universally used over another in
all situations. The selection of the proper analysis method depends upon a variety of factors including
information available, time of analysis, capabilities of the methodology, and time, funds and effort allocated to the analysis. This paper presents computerized schedule analysis programmed that use daily windows analysis method as it recognized one of the most credible methods, and it is one of the few techniques much more likely to be accepted by courts than any other method. A simple case study has been implemented to demonstrate the accuracy and usefulness of the proposed delay analysis model. The results of the study indicate that the outcomes of delay analyses are often not predictable that each method may yield different results. The study also revealed that depending on the time and resources available, and the accessibility of project control documentation, one method may be more practical or cost-effective.

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sun Jan 13 2019
Journal Name
Iraqi Journal Of Physics
Chaos synchronization delay in semiconductor lasers with optoelectronic feedback
...Show More Authors

In this work we reported the synchronization delay in
semiconductor laser (SL) networks. The unidirectional
configurations between successive oscillators and the correlation
between them are achieved. The coupling strength is a control
parameter so when we increase coupling strength the dynamic of the
system has been change. In addition the time required to synchronize
network components (delay of synchronization) has been studied as
well. The synchronization delay has been increased by mean of
increasing the number of oscillators. Finally, explanation of the time
required to synchronize oscillators in the network at different
coupling strengths.

View Publication Preview PDF
Crossref
Publication Date
Mon Apr 05 2021
Journal Name
Solid State Technology
Genetic Algorithms in Construction Project Management: A Review
...Show More Authors

Genetic algorithms (GA) are a helpful instrument for planning and controlling the activities of a project. It is based on the technique of survival of the fittest and natural selection. GA has been used in different sectors of construction and building however that is rarely documented. This research aimed to examine the utilisation of genetic algorithms in construction project management. For this purpose, the research focused on the benefits and challenges of genetic algorithms, and the extent to which genetic algorithms is utilised in construction project management. Results showed that GA provides an ability of generating near optimal solutions which can be adopted to reduce complexity in project management and resolve difficult problem

... Show More
View Publication Preview PDF
Publication Date
Thu Jul 20 2023
Journal Name
Ibn Al-haitham Journal For Pure And Applied Sciences
Fractional Pantograph Delay Equations Solving by the Meshless Methods
...Show More Authors

This work describes two efficient and useful methods for solving fractional pantograph delay equations (FPDEs) with initial and boundary conditions. These two methods depend mainly on orthogonal polynomials, which are the method of the operational matrix of fractional derivative that depends on Bernstein polynomials and the operational matrix of the fractional derivative with Shifted Legendre polynomials. The basic procedure of this method is to convert the pantograph delay equation to a system of linear equations and by using, the operational matrices we get rid of the integration and differentiation operations, which makes solving the problem easier. The concept of Caputo has been used to describe fractional derivatives. Finally, some

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Tue Nov 08 2022
Journal Name
Buildings
An Experimental Study of Granular Material Using Recycled Concrete Waste for Pavement Roadbed Construction
...Show More Authors

Rapid worldwide urbanization and drastic population growth have increased the demand for new road construction, which will cause a substantial amount of natural resources such as aggregates to be consumed. The use of recycled concrete aggregate could be one of the possible ways to offset the aggregate shortage problem and reduce environmental pollution. This paper reports an experimental study of unbound granular material using recycled concrete aggregate for pavement subbase construction. Five percentages of recycled concrete aggregate obtained from two different sources with an originally designed compressive strength of 20–30 MPa as well as 31–40 MPa at three particle size levels, i.e., coarse, fine, and extra fine, were test

... Show More
View Publication
Scopus (8)
Crossref (6)
Scopus Clarivate Crossref
Publication Date
Sun Jan 01 2023
Journal Name
Technologies And Materials For Renewable Energy, Environment And Sustainability: Tmrees22fr
Study the contrast of thermal expansion behavior for PMMA denture base, single and hybrid reinforced using the thermomechanical analysis technique (TMA)
...Show More Authors

View Publication Preview PDF
Scopus (1)
Crossref (1)
Scopus Crossref
Publication Date
Wed Apr 05 2023
Journal Name
Journal Of Engineering
Construction Time-Cost Optimization Modeling Using Ant Colony Optimization
...Show More Authors

In the field of construction project management, time and cost are the most important factors to be considered in planning every project, and their relationship is complex. The total cost for each project is the sum of the direct and indirect cost. Direct cost commonly represents labor, materials, equipment, etc.
Indirect cost generally represents overhead cost such as supervision, administration, consultants, and interests. Direct cost grows at an increasing rate as the project time is reduced from its original planned time. However, indirect cost continues for the life of the project and any reduction in project time means a reduction in indirect cost. Therefore, there is a trade-off between the time and cost for completing construc

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Sun Jul 09 2023
Journal Name
Journal Of Engineering
Improving the Performance of Construction Project Information and Communication Management Using Web-Based Project Management Systems (WPMSs)
...Show More Authors

This paper presents a brief study undertaken for improving the performance of information and communication management of construction projects through investing in information and communication technologies (ICT). The work aims at first to investigate and diagnose the problems, challenges, weaknesses, and inefficiencies related to information and communication management in projects in the construction industry of Iraq. Studying the diagnosed matters and the different solutions of ICT to improve project management performance is following the investigation process. The research presents a technological system suggested to process a lot of the diagnosed problems, challenges, weakness, and inefficiencies of the construction projects and t

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Mon Mar 08 2021
Journal Name
Baghdad Science Journal
First Order Nonlinear Neutral Delay Differential Equations
...Show More Authors

The author obtain results on the asymptotic behavior of the nonoscillatory solutions of first order nonlinear neutral differential equations. Keywords. Neutral differential equations, Oscillatory and Nonoscillatory solutions.

View Publication Preview PDF
Publication Date
Fri Jul 01 2022
Journal Name
Journal Of Engineering
An Applying the Delphi Technique for Eliciting Criteria in Equipment and Materials Used in Highway Construction Projects
...Show More Authors

This article aims to establish and evaluate standards for critical equipment and materials in highway projects in Iraq. Delphi technique has been used to analyze, explore, and discover the main criteria and sub-criteria that affect equipment and materials in highway construction projects in Iraq. To determine the correct response to the criteria presented in this study, a program (IBM, SPSS/V25) was used to assess the main criteria and sub-criteria using the mean score (MS) and standard deviation (SD) technique, as well as to check reliability using Cronbach's alpha factor (α). The experts' qualifications and the extent to which the person is ready to commit are both important factors in panel selection. The design of a

... Show More
View Publication Preview PDF
Crossref (3)
Crossref
Publication Date
Tue Dec 01 2009
Journal Name
Iraqi Journal Of Physics
Construction of Anisotype CdS/Si Heterojunction and Lineup Using I-V and C-V Measurements
...Show More Authors

Near-ideal p-CdS/n-Si heterojunction band edge lineup has been investigated for the first time with aid of I-V and C-V measurements. The heterojunction was manufactured by deposition of CdS films prepared by chemical spray pyrolysis technique (CSP) on monocrystalline n-type silicon. The experimental data of the conduction band offset Ec and valence band offset Ec were compared with theoretical values. The band offset Ec=530meV and Ev=770meV obtained at 300K. The energy band diagram of p-CdS/n-Si HJ was constructed. C-V measurements depict that the junction was an abrupt type and the built-in voltage was determined from C-2-V plot

View Publication Preview PDF