CONSTRUCTION DELAY ANALYSIS USING DAILY WINDOWS TECHNIQUE
...Show More Authors

Delays occur commonly in construction projects. Assessing the impact of delay is sometimes a contentious
issue. Several delay analysis methods are available but no one method can be universally used over another in
all situations. The selection of the proper analysis method depends upon a variety of factors including
information available, time of analysis, capabilities of the methodology, and time, funds and effort allocated to the analysis. This paper presents computerized schedule analysis programmed that use daily windows analysis method as it recognized one of the most credible methods, and it is one of the few techniques much more likely to be accepted by courts than any other method. A simple case study has been implemented to demonstrate the accuracy and usefulness of the proposed delay analysis model. The results of the study indicate that the outcomes of delay analyses are often not predictable that each method may yield different results. The study also revealed that depending on the time and resources available, and the accessibility of project control documentation, one method may be more practical or cost-effective.

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Wed Mar 01 2023
Journal Name
Iaes International Journal Of Artificial Intelligence (ij-ai)
Design and implementation monitoring robotic system based on you only look once model using deep learning technique
...Show More Authors

<span lang="EN-US">The need for robotics systems has become an urgent necessity in various fields, especially in video surveillance and live broadcasting systems. The main goal of this work is to design and implement a rover robotic monitoring system based on raspberry pi 4 model B to control this overall system and display a live video by using a webcam (USB camera) as well as using you only look once algorithm-version five (YOLOv5) to detect, recognize and display objects in real-time. This deep learning algorithm is highly accurate and fast and is implemented by Python, OpenCV, PyTorch codes and the Context Object Detection Task (COCO) 2020 dataset. This robot can move in all directions and in different places especially in

... Show More
View Publication
Scopus (12)
Crossref (4)
Scopus Crossref
Publication Date
Tue Nov 09 2021
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
The role of integration between the earned value management model and the value flow map in rationalizing the costs of construction projects: applied research in Al-Rasheed General Company for Construction Contracting
...Show More Authors

The research problem is that most of the construction projects exceed the planned value, due to the failure to implement the plans on time. The current study aims to monitor the implementation of the project and for each of the executed tasks of the table of quantities in order to detect deviations at the time they occur, evaluate the time and cost performance, and then identify the areas of waste and analyze the implementation of each task in order to diagnose the underlying problems and find possible and applicable solutions in the environment Iraqi. The research was applied in one of the companies specialized in the field of construction projects, and one of the most important conclusions reached is the possibility of applying

... Show More
View Publication Preview PDF
Publication Date
Wed Dec 01 2021
Journal Name
Professional Safety
How Technology Can Improve OSH Management in Construction
...Show More Authors

Publication Date
Sat Oct 01 2016
Journal Name
Journal Of Engineering
Intelligence in Construction between Contemporary and Traditional Architecture
...Show More Authors

The authentic traditional architecture proved that it is very convenient to the environmental and social regulations where it appeared and lasted for hundred of years.

This traditional architecture got the intelligence in providing thermal comfort for their occupants by the intelligent usage of the building materials and the intelligent planning and designs which took in consideration the climatic condition and the aerodynamics of the whole city as one ecological system starting from the cold breeze passing through its narrow streets till it enters the dwelling units and glides out through the wind catchers.

This architecture had been neglected and replaced by modern imported architecture which had collap

... Show More
View Publication Preview PDF
Publication Date
Tue Jan 01 2019
Journal Name
Cpwr
Development of a workforce sustainability model for construction
...Show More Authors

Publication Date
Thu Apr 01 2021
Journal Name
Periodicals Of Engineering And Natural Sciences (pen)
Safety management in private construction project in Iraq
...Show More Authors

View Publication
Scopus (4)
Crossref (1)
Scopus Crossref
Publication Date
Fri May 01 2020
Journal Name
Practice Periodical On Structural Design And Construction
Utilizing Emerging Technologies for Construction Safety Risk Mitigation
...Show More Authors

View Publication
Scopus (110)
Crossref (92)
Scopus Clarivate Crossref
Publication Date
Fri Mar 19 2021
Journal Name
Periodicals Of Engineering And Natural Sciences (pen)
New cost control techniques in mega construction projects
...Show More Authors

View Publication
Scopus (5)
Crossref (4)
Scopus Crossref
Publication Date
Sun Dec 16 2018
Journal Name
Al-academy
Melodic and Rhythmic Construction of Monologues in Iraq
...Show More Authors

The research studies the melodic and rhythmic characteristics of monologue, in addition to how it was transferred from the Arab homeland to Iraq and   reviewed its most prominent performers, as well as a review     of the monologue types and their propagation in the Arab homeland such as comical, dramatic, and political and guidance monologues. 

The methodological framework included: the problem of the research, the importance of the research and the objective of the research which is to uncover the melodic and rhythmic structure of the monologue in Iraq.   The limits of the research included the objective limit tackling the  art of monologue and the spatial limit which is Baghdad

... Show More
View Publication Preview PDF
Crossref
Publication Date
Thu Oct 01 2020
Journal Name
Journal Of Engineering
Financing Cost Optimization in Construction Sector: A Review
...Show More Authors

The main aim of this research is to introduce financing cost optimization and different financing alternatives. There are many studies about financing cost optimization. All previous studies considering the cost of financing have many shortcomings, some considered only one source of financing as a credit line without taking into account different financing alternatives. Having only one funding alternative powers, restricts contractors and leads to a very specific financing model. Although it is beneficial for the contractor to use a long-term loan to minimize interest charges and prevent a substantial withdrawal from his credit line, none of the existing financial-based planning models have considered long-term loans in

... Show More
View Publication Preview PDF
Crossref