PROJECT MANAGEMENT OF BALAD`S MAJOR SEWERAGE SYSTEM BY USING THE GOAL PROGRAMMING METHOD

Abstract

          The project of balad's major sewerage system is one of the biggest projects who is still in progress in salahulddin province provincial - development plan that was approved in 2013 . This project works in two parts ; the 1st is installing the sewerage networks (both of heavy sewerage & rain sewerage) and the 2nd is installing the     life – off units (for heavy sewerage & rain sewerage , as well) . the directorate of salahuiddin is aiming that at end of construction it will be able to provide services for four residential quarters , one of the main challenges that project's  management  experience is how to achieve these projects in the determined time , added cost and technical specifications although the majority of these projects have been managed with predetermined time and financial resources limits , they still need some improved strategies and more careful calculation in their time and cost management.

           This project was chosen for the following reasons , The first reason is that the project is currently stopped, because of the security and financial circumstances in salahulddin province in particular .this is a great manage time and cost when the work is resumed , and the second reason is during the progress of the project, the until it was stopped, the completion percentage was behind what it was planned originally . this highlights the need to study how to avoid these delays in future   using a scientific and logical method , and the third reason  that the project has many variables that affect the progress, which are of great importance for scientific and mathematical  methods .                                                                                                     

             To achieve this purpose the project was studied using modern scientific and mathematical methods , which are the curved part method (CPM) for project's real and accelerated timing the Primavera V6 software and the AutoCAD 2015  software . the goal is to benefit from these methods and software to establish a new work schedule for the project  . Due to the project's various and clashed (in sometimes) objectives that are have to be accomplished in a limited time , it is very important to be careful and accurate with making the right time . It was highly needed to use an efficient mathematical model that work with all these variables in the limited time allowed and according to their priorities . This mathematical method is called the Goal Programming for multi-objective mathematical models

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Mon Oct 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
The Role of Knowledge Management in Small Project Management Afield Study in Oxygen Ahli Plant in Iraq

       Most of the literature on the management and application terkzat waved the last period on large organizations was the negligence  of  knowledge management in small organizations where research aims to find out knowleddge management, small projects  In oxygen Ahli plant in Iraq, and the fact the role of knowledge management in small projects from the standpoint of employees in order to achieve this used production method results.  The results showed that knowledge management has a role in the high level of productivity during the years 2010-2013. The results showed that knowledge management has a role in the high level of productivity during the years 2

... Show More
Crossref
View Publication Preview PDF
Publication Date
Fri Jun 01 2018
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Employment cost management tools in the fast-track method Of the constructionindustries for the purpose of rationalizing costs: An applied research in the Shatt al-Diwaniya transference project General Authority for projects of irrigation and reclamation

The important factor in the success of construction projects is its ability to objective estimate of the cost of the project and adapt to the changes of the external environment, which is affected by a lot of elements and the requirements of the competitive environment. The faces of those projects are several problems in order to achieve particular goals. To overcome these difficulties has been the development of research in the last two decades and turn the focus on the role of the cost of project management, by providing information and assist management in planning and control of the budget among the main elements of the project, namely, (time-cost-quality),The research aims at the possibility of developing and implementing mechanisms

... Show More
Crossref
View Publication Preview PDF
Publication Date
Mon Mar 01 2010
Journal Name
Journal Of Economics And Administrative Sciences
The study of the effect of the use of programming in the linear programming model (applied study)

The parametric programming considered as type of sensitivity analysis. In this research concerning to study the effect of the variations on linear programming model (objective function coefficients and right hand side) on the optimal solution. To determine the parameter (θ) value (-5≤ θ ≤5).Whereas the result، the objective function equal  zero and the decision variables are non basic، when the parameter (θ = -5).The objective function value increases when the parameter (θ= 5) and the decision variables are basic، with the except of X24, X34.Whenever the parameter value increase, the objectiv

... Show More
Crossref
View Publication Preview PDF
Publication Date
Tue Jun 30 2020
Journal Name
Journal Of Economics And Administrative Sciences
Using the Critical Path Method (CPM) for scheduling the project (paving the Amil Sayid Al-Ayyam Street with a length of 1.25 km) In terms of Decresing the time

The implementation of the concept of project scheduling in the organizations generally requires a set of procedures and requirements, So, most important of all is the understanding and knowledge of the tools and techniques which are called the methods of scheduling projects. Consequently, the projects of the municipality administration in the holy governorate of Karbala suffer from the problem of delaying their projects and chaos in the ways of implementation. To provide assistance to this directorate and to demonstrate how to schedule projects using one of the advanced scientific methods that proved their ability to schedule any project and its potential to accelerate the time of completion, as well as ease of use and effectiven

... Show More
Crossref
View Publication Preview PDF
Publication Date
Thu Apr 30 2020
Journal Name
Journal Of Economics And Administrative Sciences
Designing an electronic program for the Assessment of project management in accordance with the methodology (PMBOK)

The research aims to design an electronic program that allows users to assess the possibility of different practices for projects management professional according to the PMBOK methodology)) and using the requirements Data mentioned in the "knowledge and experience in project management Evaluation guide" issued by the professional Institute of project management According to the results of this program will be electronic The possible classification of project management in terms of both (proficiency_ perform tasks) as less than the desired level or within or above average in terms of best practices, and finally a number of recommendations to overcome the possible shortcomings. The most important is the need to enrich the service

... Show More
Crossref
View Publication Preview PDF
Publication Date
Mon Dec 01 2014
Journal Name
Journal Of Economics And Administrative Sciences
Material Requirements Planning (MRP) for Electric Geyser Product by Using Goal Programming\ applicative research in the general company of electrical industrialization

Material Requirements Planning System (MRP) is considered as one of the planning and controlling of production and inventory systems which is used to prepare plan of the final production requirements and its parts of subcomponents raw materials and the time at which it was needed for the purpose of preparing orders of production and purchase.

The problem of the present work is represented in the general company of electrical industrialization adoption of traditional methods and personal experience of the process of the products and\or purchase quantity and inventory quantities and limiting the required time for acquiring the required quantities of the materials and parts used in the finish product of the

... Show More
Crossref
View Publication Preview PDF
Publication Date
Tue Mar 30 2021
Journal Name
Journal Of Economics And Administrative Sciences
Designing a Quality System using the Goals Programming Method -An Applied Research

Due to the continuous development in society and the multiplicity of customers' desires and their keeping pace with this development and their search for the quality and durability of the commodity that provides them with the best performance and that meets their needs and desires, all this has led to the consideration of quality as one of the competitive advantages that many industrial companies compete for and which are of interest to customers and are looking for. The research problem showed that the Diyala State Company for Electrical Industries relies on some simple methods and personal experience to monitor the quality of products and does not adopt scientific methods and modern programs. The aim of this research is to desi

... Show More
Crossref
View Publication Preview PDF
Publication Date
Thu Mar 30 2023
Journal Name
Journal Of Economics And Administrative Sciences
Using the Critical Path Method to Find Time of Constriction for Helicopters Airport Project in the Oil Fields

This research is considered one of the important researches in Maysan Governorate, as it focuses on the construction of helicopter airport project in the oil fields of the Maysan Oil Company, where the oil general companies in Maysan Governorate suffer from the cost of transporting the foreign engineering experts and the governing equipment of sustaining oil industry from Iraq's international airports to oil fields and vice versa. Private international transport companies transport foreign engineering from the oil fields to Iraqi airports and vice versa, and other international security companies take action to provide protection for foreign engineering experts during transportation. Hence, this process is very costly.

 &nbs

... Show More
Crossref
View Publication Preview PDF
Publication Date
Tue Sep 01 2009
Journal Name
Journal Of Economics And Administrative Sciences
Determine the optimal decision in the process of production planning usingDynamic programming style

The operation of production planning is a difficult operation and it's required High effect and large time especially it is dynamic activity which it's basic variables change in continuous with the time, for this reason it needs using one of the operation research manner (Dynamic programming) which has a force in the decision making process in the planning and control on the production and its direct affect on the cost of production operation and control on the inventory.

Crossref
View Publication Preview PDF
Publication Date
Fri Jul 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Using system dynamics model and the statistical indicators for Road Map of "Green government departments" project In Iraq

Abstract                                                         

The issue of the protection of the environment is a shared responsibility between several destinations and sectors, and constitutes a main subject in which they can achieve sustainable development. In the sectors of government programs can be set up towards the establishment of the government sector to the green environment, so to be the implementati

... Show More
Crossref
View Publication Preview PDF