بناء إنموذج رياضي لتعظيم عائد الشركة الإنتاجية بإستعمال البرمجة الكسرية الخطية الصحيحة – مع تطبيق عملي
...Show More Authors

These search summaries in building a mathematical model to the issue of Integer linear Fractional programming and finding the best solution of Integer linear Fractional programming (I.L.F.P) that maximize the productivity of the company,s revenue by using the largest possible number of production units and maximizing denominator objective which represents,s proportion of profits to the costs, thus maximizing total profit of the company at the lowest cost through using Dinkelbach algorithm and the complementary method on the Light industries company data for 2013 and comparing results with Goal programming methods results.

It is clear that the final results of resolution and Dinkelbach algorithm and complementary method are very near and maximizing proportion is equal, while, Goal programming methods are less.

From this, we can exclude that the Integer linear Fractional programming considers the best one, this result is logical because goal programming is trying to create harmony to achieve the goal of contrasting, This is considered as a model in the model to maximize the return on any company productivity.

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Sat Mar 01 2014
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
The use of technology review and evaluate programs PERT to improve the cost method on the basis of activity: بحث تطبيقي في الشركة العامة للصناعات النسيجية /واسط
...Show More Authors

Suffer most of the industrial sector companies from high Kperfi magnitude of the costs of industrial indirect, lack of equitable distribution of these costs on the objectives of cost, increased competition, and the lack of proper planning in line and changes faced by the industrial sector (general) and sample (private), as well as the difficulty in re- directing efforts to improve profitability and in-depth analysis of activities, and to identify untapped resource activities, then link these activities to the final products  The research aims to apply the technology review and evaluate programs with the method (ABC) through the application stages of planning, scheduling and control and a comparison to get to the products of dev

... Show More
View Publication Preview PDF
Publication Date
Tue Aug 03 2021
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
The role of coordination and joint cooperation in raising the quality of auditing in accordance with the INTOSAI standard(9150 (: Applied research in the General Company for Marketing Medicines and Medical Appliances - Kimadia
...Show More Authors

The process of coordination and joint cooperation between SAIs and internal auditors in the public sector is considered one of the very important matters in performing efficient audits and are of high quality, especially if this coordination and cooperation is implemented in accordance with international standards, as it leads to avoiding duplication in auditing work. And the distribution of work in a distribution that achieves the objectives of auditing in general and is of general benefit to the economic unit.

The research problem lies in the weakness of the relationship between internal auditing and external auditing as a result of not applying INTOSAI Standard (9150) coordination and joint cooperation

... Show More
View Publication Preview PDF
Publication Date
Thu Nov 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Effect the Natural Lighting In The Visual Comfort & Workers Satisfaction in Industrial Companies
...Show More Authors

Energy crisis and the requirements of health and feel good, all this renewed attention to the importance of natural lighting in all kinds of factories.
    Research problem was how to achieve the plant's own natural outlets visual comfort and satisfaction of workers in
Companies, the industries of cotton and general al-fedaa.

     The research compuns address the impact of daylight to provide visual comfort in the factory. Indeed, the light must be treated very carefully, and natural lighting should be thinking from the perspective of the occupants of the plant and not wishing to view from the outsid

... Show More
View Publication Preview PDF
Crossref
Publication Date
Wed Aug 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Prepare a plan for the Total Productive Maintenance in the light of the concurrent engineering A Field Study in AL-Askandria General Company Machanical Industries and AL-Musaib Electric Power Station
...Show More Authors

           Strives Total Productive Maintenance  to increase the overall effectiveness of the equipment through the early involvement in the design and manufacture of equipment productivity. It also operates in an environment of simultaneous engineering work on the synchronization of activities to take advantage of early information by maintenance engineers, design, operation, and that helps to reduce the faults and facilitate future maintenance tasks.

    Has adopted a search in the theoretical concept of the total maintenance productivity and concurrent engineering activities carried out during which the conjunction a

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Fri Mar 01 2013
Journal Name
Journal Of Economics And Administrative Sciences
Balancing the Multi Assembly line Using Ranked Positional Weight and COMSOAL Algorithms: Case Study at the Sewing line Factory (7) /the General Company for Leather Industries (GCLI/ Baghdad)
...Show More Authors

      The problem of multi assembly line balancing appears as one of the most prominent and complex type of problem. The research problem of this dissertation is concerned with choosing the suitable method that includes the nature of the processes of the multi assembly type of the sewing line at factory no. (7). The State Company for Leather Manufacturing. The sewing line currently suffers from idle times at work stations which resulted in low production levels that do not meet the production plans. The authors have devised a flexible simulation model which uses the uniform distribution to generate task time for each shoe type produced by the factory. The simulation of the multi assembly line was based on assigni

... Show More
View Publication Preview PDF
Crossref
Publication Date
Fri Apr 12 2019
Journal Name
Journal Of Economics And Administrative Sciences
Balanced Scorecard (BSC) role And Six Sigma in improving strategic performance A sample study of the members of the General Company for Northern Cement
...Show More Authors

Assessing performance efficiency is critical to the management need for oversight, planning, and continuous periodic evaluation of the multiple activities of Northern Cement State Company in order to determine the level of achievement of the objectives set, and to correct the deviations and delays that the evaluation shows and limitation of liability. What cannot be measured cannot be managed. The aim of this research is to highlight the impact of using BSC, financial and non-financial, to give comprehensive and clear picture of the company's performance and to measure the quality of its performance by using six-sigma and the level of deviations in achieving the planned goals. Therefore, four-key hypotheses were formulated for th

... Show More
View Publication Preview PDF
Crossref
Publication Date
Wed Oct 17 2018
Journal Name
Journal Of Economics And Administrative Sciences
Solve the fuzzy Assignment problem by using the Labeling method
...Show More Authors

The Assignment model is a mathematical model that aims to express a real problem facing factories and companies which is characterized by the guarantee of its activity in order to make the appropriate decision to get the best allocation of machines or jobs or workers on machines in order to increase efficiency or profits to the highest possible level or reduce costs or time To the extent possible, and in this research has been using the method of labeling to solve the problem of the fuzzy assignment of real data has been approved by the tire factory Diwaniya, where the data included two factors are the factors of efficiency and cost, and was solved manually by a number of iterations until reaching the optimization solution,

... Show More
View Publication Preview PDF
Crossref
Publication Date
Sun Feb 28 2021
Journal Name
Journal Of Economics And Administrative Sciences
Availability Assessment of theManaging the Audit Program. According to the Specification Standard (ISO 19011:2018): A case study in Ministry of Construction Housing and General Municipalities
...Show More Authors

 

The research aims to study the reliability of government institutions, including the audit directors, which are one of the most important oversight formations in the Ministry of Construction, Housing and Public Municipalities, on which the responsibility for comprehensive auditing of all the Ministry's (municipalities) formations falls on the Managing the Audit Program according to the specification (ISO 19011: 2018) to improve the audit performance which requires compliance with the application of the audit management system in accordance with the standard Specification (ISO 19011: 2018), depending on the methodology of the case study, and using of checklists, which were chosen ac

... Show More
View Publication Preview PDF
Crossref
Publication Date
Sun May 02 2021
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
The effect of applying lean construction tools to improving the results of the earned value management model: Applied research in Al-Rasheed General Company for Construction Contracting
...Show More Authors

Contracting companies play a prominent role today in economic activity, due to their contribution to the implementation of major construction projects which together constitute the infrastructure of society. Most construction projects also suffer from exceeding the time and cost specified and planned for the completion of the project, and this comes for several reasons, including the work environment, country conditions, The method of managing project costs and the techniques used in its implementation Accordingly, the concepts of lean construction came, which help in addressing the causes of waste, both in time and cost, in addition to the fact that project management needs techniques that are useful in controlling the control and manag

... Show More
View Publication Preview PDF
Publication Date
Sun Dec 01 2013
Journal Name
Journal Of Economics And Administrative Sciences
Assess the Reality of the Process of Applying the strategic Innovation In Business organizations : A prospective Study of comparative analysis in anumber of business organizations the Iraqi Industrial
...Show More Authors

Abstract :

      The research aims to Estimate the Strength of Strategic Innovation application in terms of application strength , and on the overall level in number of Iraqi Industrial business organizations . After wards determine whether their is differerences among those organizations in application process for the dimensions , and for the overall process .

      The Research revealed number of conclusions including that the process of strategic innovation is applied in a good Level , and demonstrates the desier of the industrial companies Leaders to Launch beyond the familiar products , and to provide new products that