Public Procurement Crisis of Iraq and its Impact on Construction Projects
...Show More Authors

 

The public procurement crisis in Iraq plays a fundamental role in the delay in the implementation of construction projects at different stages of project bidding (pre, during, and after). The procurement system of any country plays an important role in economic growth and revival. The paper aims to use the fuzzy logic inference model to predict the impact of the public procurement crisis (relative importance index and Likert scale) was carried out at the beginning to determine the most important parameters that affect construction projects, the fuzzy analytical hierarchy process (FAHP) to set up, and finally, the fuzzy decision maker's (FDM) verification of the parameter for comparison with reality. Sixty-five construction projects in Iraq have been selected, and the most crucial crisis variables were used for calculating the weights and their importance, using the fuzzy logic inference model to verify the crisis parameters and the extent of their impact in preparation for predicting the mathematical model of public procurement parameters. After the algorithm had been completed, it was noted that the fast, messy genetic algorithm produced a little difference between training and testing (0.012% and 0.0057%), which is more reliable for predicting mean results from models. The paper’s major conclusion is that 18 crisis factors in public procurement through different stages affect construction projects in Iraq.

 

Crossref
View Publication Preview PDF
Quick Preview PDF
Publication Date
Wed Feb 01 2023
Journal Name
Journal Of Engineering
Procurement Management of Power Plants Construction Projects in Iraq
...Show More Authors

The government of Iraq states that despite the massive amounts invested in the power generating sector, the country has been plagued by power outages for more than three decades; One of the most common sources of the problem and significant impact on the waste of public funds in contractual processes. The Ministry of Planning issued the sectorial
specialized standard bidding documents (SSBD) of Design, Supply, and Installation of the Electromechanical Works (DSIoEW), which is primarily designed to support the Ministry of Electricity (MoE) by developing economic projects to improve the contractual process that led to raisings Iraqi electricity generation field. The research evaluates the impact of
applying the SSBD-DSIoEW for

... Show More
View Publication Preview PDF
Crossref (1)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of Engineering
Developing Crisis Management System for Construction Projects in Iraq
...Show More Authors

Construction is a complicated process that takes place in an almost uncontrollable environment. Although projects can be carefully planned in advance in principle, there is a chance that unforeseen events and crises can disrupt these plans, affecting project development. Because the initial investment expenditures in construction projects are so large, they may be quickly influenced by crises, resulting in significant financial losses. The 2014 financial crisis was one of the most prominent crises that Iraq faced, which significantly impacted various activities in general and the construction industry in particular. Despite the importance of crisis management systems, the researchers found a great lack of local studies l

... Show More
View Publication Preview PDF
Crossref (6)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of Engineering
Developing Crisis Management System for Construction Projects in Iraq
...Show More Authors

Construction is a complicated process that takes place in an almost uncontrollable environment. Although projects can be carefully planned in advance in principle, there is a chance that unforeseen events and crises can disrupt these plans, affecting project development. Because the initial investment expenditures in construction projects are so large, they may be quickly influenced by crises, resulting in significant financial losses. The 2014 financial crisis was one of the most prominent crises that Iraq faced, which significantly impacted various activities in general and the construction industry in particular. Despite the importance of crisis management systems, the researchers found a great lack of local studies looking at cr

... Show More
View Publication
Crossref (6)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
Journal Of The Mechanical Behavior Of Materials
Identification of the main causes of risks in engineering procurement construction projects
...Show More Authors
Abstract<p>Many risks have adverse consequences for construction projects’ objectives such as quality, schedule, and cost. As engineering procurement construction (EPC) contracts gradually become one of the most common types used in implementing major large-scale construction projects, identifying common risk types and analyzing their root causes is important for developing measures to decrease and eliminate future risks in these types of contracts. The information about the main causes of risks was collected <italic>via</italic> well-structured questionnaires addressed to construction sector professionals and preparing lists of main potential risks in EPC/construction projects throu</p> ... Show More
View Publication
Crossref (1)
Crossref
Publication Date
Tue Dec 01 2015
Journal Name
Journal Of Engineering
Valuation the Impact of Risks on the Goals and the Safety of Construction Projects in Iraq
...Show More Authors

Construction projects have a special nature and affect them many factors making them exposed to multiple risks as a result of the length of the implementation period and the multiplicity of stages, starting from the decision stage through implementation until the final delivery, which leads to increased uncertainty and the likelihood of risk.
The process of analysis and risk management is one of the effective and productive methods that are used in managing the construction projects for the purpose of increasing the chances of ending the project successfully in terms of cost, time and quality and at the lowest possible problems.

The research aims first to the effective planning for analysis and risk managemen

... Show More
View Publication Preview PDF
Publication Date
Mon Feb 01 2021
Journal Name
Journal Of Engineering
Assessment of the Cost and Time Impact of Variation Orders on Construction Projects in Sulaimani Governorate
...Show More Authors

Variation orders are an on-going phenomenon in construction and industry projects worldwide, particularly in the province of Sulaimani, where the project's damage from cost and schedule overrun because of variation orders. However, the effect on project costs and time overrun of variation order has yet to be identified. This study evaluates the impact of variation orders on the cost and time off in the Sulaimani governorate. Two hundred twenty-eight projects from various construction sectors built between 2007-2012 were adopted to calculate the contract cost and schedule overruns due to variation orders. Data analysis was applied in the study were descriptive statistics. One-way ANOVA was also applied to determine w

... Show More
View Publication Preview PDF
Crossref (6)
Crossref
Publication Date
Sat Aug 01 2015
Journal Name
Journal Of Engineering
Development of a Blueprint Impact System of the risks on construction projects Implementation
...Show More Authors

In Production and Operations Management the specialists  have  tried to develop a strategy to counter the risks arising from the activities of the organization and of waste of various types and therefore the risk management in the contemporary framework represents a phenomenon of new quality, and can not be this phenomenon to take practical dimensions, but the development of culture of the organization towards the risks and deal with all aspects and paint ways to address them within an integrated program, and requires new skills and systems provide accurate information capable of coordination between the various parties within the organization.

     The research aims to develop a blu

... Show More
View Publication Preview PDF
Publication Date
Thu Oct 01 2020
Journal Name
Green Engineering
Sustainability and recovery project management implementation on construction projects in Iraq
...Show More Authors

Scopus (1)
Scopus
Publication Date
Mon Oct 02 2023
Journal Name
Journal Of Engineering
Main Delay Factors of Implementation EPC Construction Projects in Iraq
...Show More Authors

This essay aims to highlight the most important issues and difficulties facing implementing large projects that follow the turn-key method, considered one of the types of contractual methods in Iraq, especially for large and complex projects requiring speedy completion. The projects implemented in this way face delays and delays in completion, which led to the lack of benefit from the projects for which they were implemented, especially those affecting the lives of citizens within the health sector. The case study dealt with the construction of hospitals with multi-bed capacities within multiple governorates in Iraq, With large financial allocations within the federal budget of the Government of Iraq over several years.

... Show More
View Publication Preview PDF
Crossref (2)
Crossref
Publication Date
Sat Jan 01 2022
Journal Name
International Journal Of Management And Enterprise Development
Studying The Decision-Making State and Impact in Iraqi Construction Projects