Performance Evaluation of the Investment Projects during the Implementation Phase (Najaf province as a case study)

The construction project is a very complicated work by its nature and requires specialized knowledge to lead it to success. The construction project is complicated socially, technically and economically in its planning, management and implementation aspects due to the fact that it has many variables and multiple stakeholders in addition to being affected by the surrounding environment. Successful projects depend on three fundamental points which are cost-time, performance and specifications. The project stakeholder's objective to achieve best specifications and the cost-time frame stipulated in the contract.

The question is, was the optimum implementation accomplished? The provision for the success of the project is how are the daily activities managed by the three stakeholders of the project (contractor, owner, and consultant) and their technical and practical capability to attain the balance of the project fundamental points (cost, time and quality) taking into account the project objectives that were set by the owner. Despite the way, logical framework management and project’s major steps there is a group of elements which become major measures to determine the success or failure of the project, the research interested in these elements by a thorough study of references related to the success of a constructional project. To reinforce the theoretical study a field assessment of the housing project; this led to the recognition of the major elements that caused breaches of the evaluation criteria.

The closed questionnaire and the regular forms based on the data and information collected through the theoretical review and the closed questionnaire to conclude and examine some concepts related by assessing the quality of building materials used in residential investment projects through the stages (planning - design-implementation)

Through the research a lot of deductions were made, the most important is that there cannot be an evaluation system without having a holistic monitoring system in Iraq. It was also deduced that the most important source of project failure is not allocating enough time to the planning phase. Some other recommendations and suggestions for future studies were made also.

 

View Publication Preview PDF
Quick Preview PDF
Publication Date
Mon Oct 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Evaluate the implementation of the investment plan projects A study on the field of the plan projects for the period 2013-2016

The main problem of this research is the delay of implementation of the investment plan projects for the period (2013-2016) and the weakness of the staff ability in the ministries and they don’t have the sufficient experience to carry out the implementation process.

Therefore, the research aims to evaluate the implementation of programs and projects of the investment plan in a manner consistent with the objectives set for them without any wasteful of efforts, time and money. And then identify the problems and obstacles to determine the deviations of the implementation of the specific for each sector according to the criteria of evaluation and the form of cost, quality, time and implementation.<

... Show More
Crossref
View Publication Preview PDF
Publication Date
Thu Feb 01 2018
Journal Name
Journal Of Economics And Administrative Sciences
Developing the investment budgeting through evaluation of investment projects

The aim of the research is to determine the impact of evaluating the investment projects in the development and preparation of investment budgets prepared by the economic units, since the investment projects are of an important and vital nature of the economic units, because these projects include the length of time for preparation and implementation and the accompanying period of this risk and uncertainties as well as need To the many funds to complete the project , The process of evaluating the implemented projects, which have been prepared an investment budget previously will contribute to the extent of matching the estimated data with the actual results or deviations, which is a step to avoid these errors in future p

... Show More
Crossref
View Publication Preview PDF
Publication Date
Thu Apr 25 2019
Journal Name
Iraqi Journal Of Market Research And Consumer Protection
PATTERN OF INVESTMENT PROJECTS IN THE INVESTMENT ENVIRONMENT: PATTERN OF INVESTMENT PROJECTS IN THE INVESTMENT ENVIRONMENT

That the building of the national economy depends on the extent of the possibility of transition from the rent economy seeking to increase GDP (GDP1), and the tendency to manage projects with external sources of funding, or allow projects with foreign capital is a necessity. The strategic challenges faced by the economy in countries that have experience in investment projects have faced several factors internal and external for a period of time and not a few and the pressures and difficulties and failures have affected in one way or another on the development work in that country. On this basis, the stakeholders have a role to pay attention to the issue of the feasibility of the pattern of foreign investment in the investment environment

... Show More
View Publication Preview PDF
Publication Date
Mon Feb 01 2016
Journal Name
Journal Of Economics And Administrative Sciences
Evaluation of real estate investment projects with framework theory of real options: A case study in the shopping center project (Baghdad Mall)

 

Focused research aims to provide a framework cognitive analytical nature of real estate investments and how they evaluated in the light of the assessment tools of modern theory of real options, and the possibility to rely on that theory in the detection of the true value of projects, real estate investments that would maximize the value of the investment decision taken, and the analysis of those projects that arise in the real estate markets and environments is the organization, which she was to make sure cases and high-risk, compared with entrances techniques, discounted cash flow (net present value). Based on the assumption lies in the possibility of the application of the implic

... Show More
Crossref (1)
Crossref
View Publication Preview PDF
Publication Date
Tue Mar 01 2016
Journal Name
Journal Of Engineering
Critical Success Factors in Construction Projects (Governmental Projects as a Case Study)

The importance of the construction sector and its Great role in the provision of services and infrastructure, reduce poverty, improve living conditions and improve the economic situation in the country, impose attention to the way in which the projects implemented for its improvement and to get successful projects. The objective of this research was to determine the criteria for success as well as critical success and failure factors that have a significant impact on project success. A selected 75 engineer (department managers, project managers and engineers) are asked to fill  the questionnaire form, Sixty-seven valid questionnaire forms were analyzed statistically to get search results, which were as follows : Twe

... Show More
View Publication Preview PDF
Publication Date
Fri Jan 01 2016
Journal Name
Arpn Journal Of Engineering And Applied Sciences
Scopus (1)
Scopus
Publication Date
Sat Jun 01 2019
Journal Name
Journal Of Economics And Administrative Sciences
Diagnosis of factors affecting the strategic implementation of sewage projects ( Case study in General Directorate of sewage projects )

  This  Research aim to identify the factors affecting the strategic implementation of sewage projects and to seek to activate the real follow-up of projects to identify the factors that accompany their implementation, The study included a sample of the projects of the investment plan implemented for the Directorate General of sewage in the governorates of Iraq, which was completed during the six years period (2010-2016). The sample of the research was four projects: The project of implementation and processing of the treatment plant and the lifting station and the conveyor line for the project of IMARA/The third stage/Al-Sanaf marshland , The project of the processing and implementation of the treatment plant with the

... Show More
Crossref
View Publication Preview PDF
Publication Date
Mon Jun 01 2009
Journal Name
Journal Of Economics And Administrative Sciences
Use sensitivity analysis in evaluating projects Investment under the conditions of risk and uncertainty Case study of glass bottles project in Anbar province

This paper studies the investment project evaluation under the condition of uncertainty. Evaluation of investment project under risk and uncertainty is possible to be carried out through application of various methods and techniques. The best known methods are : Risk-adjusted discount rate , certainty equivalent method , Sensitivity analysis and Simulation method The objective of this study is using the sensitivity analysis in evaluation Glass Bottles project  in Anbar province under the condition of risk and uncertainty.

After applying sensitivity analysis we found that the glass bottles project  sensitive to the following factors (cash flow, the cost of investment, and the pro

... Show More
Crossref
View Publication Preview PDF
Publication Date
Sun Dec 01 2019
Journal Name
Journal Of Economics And Administrative Sciences
Strategic Analysis of the Reasons for the Delay of the Investment Projects of the North Oil Company / Case Study

The research aims to find a contemporary model in analyzing the reasons behind the delay of the investment plan projects suffered by the North Oil Company. This model is able to understand the environment surrounding the implementation of projects in the light of the changes facing the company at the present time, which in turn requires the need to identify the most important strengths and weaknesses Internal and external opportunities and threats using the SWOT matrix and identify the appropriate strategic alternative based on clear policy, strategies and programs to address weaknesses and look to the future prospects as the company can be stronger and more flexible environmental changes surrounding the reality of implementation

... Show More
Crossref
View Publication Preview PDF
Publication Date
Sat Sep 01 2018
Journal Name
Journal Of Accounting And Financial Studies ( Jafs )
Evaluation of the performance of scheduling The implementation of school buildings projects: (Project of the Ministry of Education No. 1)

It highlights the importance of construction projects because of its significant role in the development of society, including the buildings FEDE projects to their importance to raise the level of education through the conclusion of the special to implementation and the establishment of schools of contracts at the country level, which requires the completion of the project at less time and within the cost specified and the best quality and may highlight the importance of time on all the elements of what has an important role in setting up the project for various reasons may be the need for the use of schools as soon as possible, but the reality showed exceeded the completion of those schools could be up to 6 years and there are some cont

... Show More
Crossref
View Publication Preview PDF