This research work dealt with the problem of layout the production line of engine of fan roof at the General Company for Electrical Industries (GCEI). It was observed that the assembly line of engine was unstable and subject to severe fluctuations. In addition the execution of tasks at some stations was observed to be very fast while at other stations was slow. This phenomenon resulted into bottlenecks between workstations, idle time, and work in process. The system design was used to assign tasks to work stations according to different heuristics (Ranked Positional weight techniques, longest Task Time, Most following tasks, Shortest tasks time, Least number of following task).
The study revealed that the performance of the Ranked positional was almost identical and was better than that of others. Therefore the study recommended the arrangement of tasks by either method for this case.